Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T11BU01702

Parcel: 11612751A


Addresses:

550 N SILVERBELL RD


Inspection Status: Approved

Inspection History: STORMWATER INSTALL OF CONTROLS

Permit Number - T11BU01702

Inspection Description - STORMWATER INSTALL OF CONTROLS

Inspection Status - Approved

Date Description Inspector Results Comments
05/15/2012 STORMWATER INSTALL OF CONTROLS Approved 1) MET WITH SUPERINTENDENT ON SITE, DISCUSSED SWPPP, REVIEWED GRADING PLAN, AND INSPECTED PER THE NPPO.
2) ENSURE A STABILIZED ENTRANCE/EXIT IS INSTALLED AND MAINTAINED WHERE NEEDED.
3) COMPLETE INSTALLATION OF SILT SOCK ALONG NORTH PERIMETER AND ALONG EAST PROPERTY BOUNDRY.
4) MAINTAIN SEDIMENT CONTROLS THROUGHOUT CONSTRUCTION.
5) INSTALL A CONCRETE/MATERIALS WASH-OUT ON SITE WHEN APPLICABLE.
6) ENSURE FUELS/OILS, PAINTS AND OTHER CHEMICALS USED ON SITE ARE STORED PROPERLY.
7) PERFORM SELF INSPECTIONS PER YOUR SWPPP AND DOCUMENT THEM.
8) POST A COPY OF YOUR NOI AT THE ENTRANCE TO THE SITE.