Inspection History Details
Inspection Status: Approved
Inspection History: FIRE - ALARM FINAL
Permit Number - T11BU01604
Inspection Description - FIRE - ALARM FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/30/2012 | FIRE - ALARM FINAL | Approved | ||
07/27/2012 | FIRE - ALARM FINAL | Partial Approval | 1. EVERYTHING IS TESTED AND PASSED. JUST NEED AS BUILDS TO GIVE FINAL APPROVAL. | |
07/26/2012 | FIRE - ALARM FINAL | Denied | New batteries install 24 hour test started 11:00 AM Need to get as bults in for changes before final will be given. It is OKAY to move in and use building when 24 hour stand-by test is approved a temp C of O will be approved (Per Ken Brouillete). |
|
07/25/2012 | FIRE - ALARM FINAL | Denied | 24 Hour battery stand by failed start over agian | |
07/19/2012 | FIRE - ALARM FINAL | Partial Approval | 6th floor tested all smokes in rooms, still need to check all dampers. | |
07/18/2012 | FIRE - ALARM FINAL | Denied | Troulbes with dampers not closing on 6th, 5th, 3rd, and 1st floors. | |
07/17/2012 | FIRE - ALARM FINAL | Partial Approval | Flows and tampers tested in stairwell: 1st fl 39.00 sec, 2nd fl 31 sec., 3rd fl 38 sec., 4th fl 34 sec., 5th fl 34 sec., 6th fl 42 sec. All tampers tested in fire pump room passed. |
|
07/16/2012 | FIRE - ALARM FINAL | Denied | 1.) All smokes shall be installed per approved plans 4" min - 12" max from ceiling. 2.) All smokes shall be installed per approved plans 3' away from diffusers (intake and exhaust). |