Inspection Status: Approved
Inspection History: ENGINEERING PRE-CONSTRUCTION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/30/2012 | ENGINEERING PRE-CONSTRUCTION | Approved | ||
| 01/26/2012 | ENGINEERING PRE-CONSTRUCTION | Continued | MET WITH SUPERINTENDENTS ( ED/ BILL W/ BARKER MORISSEY) TO DISCUSS SITE WORK AND THE CONSTRUCTION OF THE NEW SHOE CARNIVAL. CONTRACTOR HAS STARTED SITE WORK CONSTRUCTION ON COMMON AREAS AND ACCESS SIDE WALKS SHOWN ON THE GRADING PLAN, TO INCLUDE A RET/DET BASIN W/ AN INLET PIPE AND OUTLET SCUPPER. STORM DRAIN PIPIE WAS INSTALLED WITHOUT INSPECTION FROM THE CITY, THEREFORE THE ENGINEER OF RECORD MUST CERTIFY THAT IT WAS INSTALLED PER THE APPROVED PLAN. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. |
|
| 12/15/2011 | ENGINEERING PRE-CONSTRUCTION | Continued | DEMO OF BLDG COMPLETE, NO CONTRACTOR NO CONSTRUCTION |