Inspection History Details
Inspection Status: Continued
Inspection History: GRADING - INTERMEDIATE
Permit Number - T11BU01351
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Continued
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/02/2013 | GRADING - INTERMEDIATE | Continued | SECOND PHASE OF SITE/GRADING ALMOST COMPLETE CONTRACTOR NEEDS TO FINISH LANDSCAPING AND STRIPING NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
|
04/18/2013 | GRADING - INTERMEDIATE | Continued | CONTRACTOR PAVING SITE NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
|
04/05/2013 | GRADING - INTERMEDIATE | Continued | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME CONTRACTOR PREPARING FOR PAVING |
|
03/14/2013 | GRADING - INTERMEDIATE | Continued | 1) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME 2) ENSURE STORM WATER SELF INSPECTIONS ARE COMPLETED PER YOUR SWPPP 3) PRIOR TO FINAL, CLEAN OUT EXISTING STORM DRAIN CATCH BASIN ALONG NORTH SIDE OF SITE |
|
02/22/2013 | GRADING - INTERMEDIATE | Continued | 1) SITE IS EXTREMELY WET, RAIN THE DAY BEFORE 2) CONTRACTOR DRILLING HOLES TO INSTALL FOOTINGS FOR PARKING AREA LIGHTING 3) SEDIMENT CONTROLS ARE IN PLACE. 4) CONSTRUCTION ENTRANCE/EXIT NEEDS TO BE RE-ESTABLISHED AND ROADWAY NEEDS SWEPT 5) NO OTHER SITE WORK AT THIS TIME |
|
02/05/2013 | GRADING - INTERMEDIATE | Continued | 1) CONTRACTOR ROUGH GRADING PARKING LOTE AREA 2) MOST PERIMETER SEDIMENT CONTROLS HAVE BEEN INSTALLED. 3) NO CHANGES AND/OR CONCERNS AT THIS TIME |
|
06/21/2012 | GRADING - INTERMEDIATE | Continued | NO ACTIVITY ON SITE AT THIS TIME | |
06/11/2012 | GRADING - INTERMEDIATE | Cancelled | NO ACTIVITY ON SITE | |
06/08/2012 | GRADING - INTERMEDIATE | Cancelled | IVRS - RI canceled | |
05/29/2012 | GRADING - INTERMEDIATE | Continued | NO ACTIVITY TODAY, NO GRADING TAKING PLACE ALONG EAST PROPERTY. NO STORM WATER CONCERNS AT THIS TIME |
|
05/16/2012 | GRADING - INTERMEDIATE | Continued | NO ACTIVITY TODAY, NO GRADING TAKING PLACE ALONG EAST PROPERTY. NO STORM WATER CONCERNS AT THIS TIME |
|
04/05/2012 | GRADING - INTERMEDIATE | Continued | 1) CHECKED RE-BAR LAYOUT FOR SCREEN WALL ALONG SOUTH SIDE OF SITE. FOOTINGS WERE DUG PER APPROVED PLANS. LAY- OUT WAS PER PLANS. 2) CONSTRUCTION ALSO STARTED ON DUAL TRASH ENCLOSURE - ENSURE 10' CLEAR WIDTH PER CELL. 3) PRIOR TO CONSTRUCTION BEGINING ON THE REMAINING SITE, ENSURE ALL STORM WATER CONTROLS ARE INSTALLED PER YOUR STORM WATER PLAN. |
|
04/02/2012 | GRADING - INTERMEDIATE | Continued | FOLLOW UP SITE INSPECTION. CONTRACTOR HAS BUILDING PERMIT WITH NO ENGINEERING INSPECTION. GRADING PERMIT SHOWS A MUCH LARGER AREA TO BE DEVELOPED. ONLY A SMALL PORTION OF THE SITE HAS BEEN COMPLETED. GRADING PERMIT WILL REMAIN OPEN UNTIL SITE WORK HAS BEEN COMPLETED. |
|
03/20/2012 | GRADING - INTERMEDIATE | Continued | NO SITE WORK BEING DONE - RAIN DAY NO STORM WATER CONCERNS AT THIS TIME |
|
03/14/2012 | GRADING - INTERMEDIATE | Continued | 1) MET WITH SUPERINTENDENT HE STATED THAT THIER AREA OF CONSTRUCTION FOR THIS PROJECT WILL EXPAND TO INCLUDE THE DEMO/CONSTRUCTION OF THE ACCESS ROAD OFF SPEEDWAY BUT NOT THE ENTIRE SITE SHOWN ON THE APPROVED GRADING PLAN. 2) SITE NEEDS TO PHASED WITH AN APPROVED PHASING PLAN TO SHOW WHAT WILL BE CONSTRUCTED, WHEN. 3) CONTRACTOR WAS TOLD TO INSTALL SEDIMENT CONTROLS ACCROSS AND DOWN STREAM OF THE AREA THRY WILL BE WORKING IN. 4) REPAIR AND REPLACE YOU DESIGNATED CONCRETE WASH OUT. |
|
03/12/2012 | GRADING - INTERMEDIATE | Continued | MET WITH CONTRACTOR, HE WANTS TO MEET WITH MIKE WHEN HE RETURNS TO DISCUSS NEW PERMIT WORK TO START. | |
02/28/2012 | GRADING - INTERMEDIATE | Continued | LOOKED AT THE FORMS FOR THE NEW CONCRETE PAVEMENT ON THE WEST SIDE OF THE EXISTING STRUCTURE. | |
02/09/2012 | GRADING - INTERMEDIATE | Continued | 1) NO PRE-CON MEETING CALLED IN, SITE ALREADY UNDER CONSTRUCTION. 2) SITE WAS PERMITTED FOR AN OVERALL PROJECT OF 4.6 AC, HOWEVER ONLY A SMALL PORTION OF THAT IS BEING DEVELOPED AT THIS TIME, < 1 AC. 3) THE SITE WILL BE PHASED AND THE CONTRACTOR WILL BE HELD RESPONSIBLE FOR WORK SHOWN ON THAT PHASE. 4) SWEEP UP TRACKED SOIL DAILY. 4) CALL FOR INSPECTION PRIOR TO PAVING |