Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER INSTALL OF CONTROLS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/28/2014 | STORMWATER INSTALL OF CONTROLS | Approved | ALL SITE/GRADING HAS BEEN STABILIZED | |
| 01/25/2013 | STORMWATER INSTALL OF CONTROLS | Continued | 1) MET WITH SUPERINTENDENT, PROJECT MANAGER, AND SWPPP CONTRACTOR ON SITE TO INITIATE PHASE II OF THE PROJECT. 2) INSTALL SEDIEMNT CONTROLS AT WALL OPENING, AND AROUND THE EXISTING STORM DRAIN CATCH BASIN AND ALONG THE WEST/SW SIDE OF THE SITE 3) INSTALL A STABILIZED CONSTRUCTION ENTRANCE/EXIT ON SITE 4) INSTALL A DESIGNATED CONCRETE/MATERIALS WASH OUT 5) POST A COPY OF YOUR NOI 6) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED |