Inspection Status: Approved
Inspection History: FIRE SPKLR - OH PIPING & HYDRO
| Date |
Description |
Inspector |
Results |
Comments |
| 07/02/2012 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Approved |
Floors 1 thur 6 OH done |
| 04/02/2012 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
6Th floor OH piping and Hydro and placment approved |
| 03/20/2012 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
5TH FLOOR 200 PSI AND PLACEMENT APPOVED. |
| 02/22/2012 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
4TH floor 200 psi and placement aproved. |
| 02/13/2012 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
3rd Floor 200 psi and placement approved. |
| 01/10/2012 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
2nd Floor 200 psi and palcement approved |
| 12/12/2011 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
First Floor - Extend one line in Com Data Room to 7.5 ft off wall. Pressure test at 200 LBS passed. All other piping on first floor approved. |