Permit: T11BU01215

Parcel: 13303301E


Addresses:

9971 E SPEEDWAY BL

Inspection Status: Approved

Inspection History: FIRE SPKLR - UG, PIPING, HYDRO

Date Description Inspector Results Comments
11/17/2011 FIRE SPKLR - UG, PIPING, HYDRO Approved 200 PSI FOR 2 HOURS DONE
11/16/2011 FIRE SPKLR - UG, PIPING, HYDRO Denied On site at 12:40 PM contractor stated that he has had the underground system pressured up at 200 PSI for over 2 hours, we walked the property checking to make sure all valves are open to stub outs and dead ends that feed sprinkler systems. Checked gauge at 1:50 PM still at 200 PSI. Contractor will be calling in permit for final 200 test on 11/17/2011 time set for 7:30 AM.
11/02/2011 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval Okay to bury piping to buildings 12 - 13- 24 - 22. Still needs 200 psi test and flush.
10/31/2011 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval Okay to bury the follwing:
Bldgs. 6-7-8 piping to stainless steel riser
Bldg. 17 - 60 feet stub out no riser
Bldg. 18 - 150 feet stub out no riser
Still need flush and 200 PSI test for 2 hours.
10/21/2011 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval OK TO BURRY BUILDINGS 1,2,3,5,23. STILL NEED PRESSURE TEST ON ALL.
10/20/2011 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval Okay to bury the following:
Bldg #4
Bldg #9
Bldg #10
Bldg #11
Still needs 200 psi test and flush
10/12/2011 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval Okay to bury stub outs for clubhouse, and buildings 1 - 2 - 3 still need 200 psi test for 2 hours and flush.