Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T11BU01043

Parcel: 107060380


Addresses:

1395 W MIRACLE MILE

Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Date Description Inspector Results Comments
03/26/2014 STORMWATER FOLLOW-UP INSP Approved
03/24/2014 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER COCNERNS AT THIS TIME
03/13/2014 STORMWATER FOLLOW-UP INSP Continued 1) ADDRESSED THE DESIGNATED PEDESTRIAN ACCESS ALONG THE EAST SIDE OF THE BLDG. RECEIVED AN UPDATED DRAWING SHOWING ELEVATIONS AND SLOPES.
2) PROVIDE APPROVAL FOR CHANGES TO THE SIZE OF THE SIDEWALK SCUPPER IN THE FAR EAST CORNER OF THE SITE
3) NEED TO RE-DIRECT STORM WATER AT CURB OPENING WHERE IT INTERSECTS WITH THE SIGN ELECTRIC CONDUIT BOX ALONG THE NORTH SIDE OF THE PARKING LOT
4) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
02/28/2014 STORMWATER FOLLOW-UP INSP Continued ENSURE STORM WATER CONTROLS REMAIN IN PLACE UNTIL SITE IS STABILIZED
02/20/2014 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
02/12/2014 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
02/11/2014 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER COCNERNS AT THIS TIME
01/24/2014 STORMWATER FOLLOW-UP INSP Continued CHECKED THE STATUS OF CONSTRUCTION
NO SITE GRADING CONCERNS AND/OR CHANGES AT THIS TIME
NO SIGNIFICANT STORM WATER COCNERNS AT THIS TIME
01/17/2014 STORMWATER FOLLOW-UP INSP Continued 1) PROVIDE A COPY OF YOUR ELEV. CERTIFICATE PRIOR TO FINAL GRADING APPROVAL
2) ENSURE PEDESTRIAN ACCESS AND EGRESS MEET ANY AND ALL DEV. STANDARDS AND ADA REQUIREMENTS THAT PERTAIN TO THIS SITE.
3) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
4) ENSURE SEDIMENT CONTROLS ARE MAINTAINED THROUGHOUT CONSTRUCTION

CALL FOR ANY CONCERNS AND/OR CHANGES MADE TO THE SITE/GRADING
01/15/2014 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
12/31/2013 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
12/20/2013 STORMWATER FOLLOW-UP INSP Continued 1) RE-INSTALL SEDIMENT CONTROLS ALONG EAST SIDE OF SITE
2) SWEEP UP TRACKED SOIL AS NEEDED
3) ENSURE STORM WATER SELF INSPECTIONS ARE ACCOMPLISHED
12/19/2013 STORMWATER FOLLOW-UP INSP Continued SEDIEMTN CONTROLS IN PLACE NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
11/27/2013 STORMWATER FOLLOW-UP INSP Continued 1) INSTALL OF SEDIMENT CONTROLS - APPROVED
2) RE-ESTABLISH WADDLE ALONG EAST PERIMETER AS SOON AS TRECH IS BACKFILLED
3) ENSURE YOU SWEEP UP TRACKED SOIL ROUTINELY
4) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED DOCUMENTED
11/20/2013 STORMWATER FOLLOW-UP INSP Continued 1) POST A SIGNED COPY OF YOUR NOI AT THE ENTRANCE TO YOUR CONSTRUCTION SITE
2) IMPLEMENT YOUR SWPPP - INSTALL SEDIMENT CONTROLS ALONG THE EAST AND WEST PERIMETERS OF THE SITE, CONTROLS MAY BE CHANGED BASED ON SITE SPECIFICS
3) INSTALL A CONCRETE/MATERIALS WASH OUT WHEN APPLICABLE
4) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED PER YOUR PERMIT.
5) SWEEP UP TRACKED SOIL OFF ADJACENT ROADWAYS AS NEEDED
6) CALL FOR RE-INSPECTION FOR INSTALL APPROVAL
08/23/2012 STORMWATER FOLLOW-UP INSP Continued NO WORK AT THIS TIME, NO CONCERNS AT THIS TIME.
08/21/2012 STORMWATER FOLLOW-UP INSP Continued NO WORK AT THIS TIME, NO STORMWATER CONCERNS AT THIS TIME.
06/29/2012 STORMWATER FOLLOW-UP INSP Continued NO CONSTRUCTION WORK AT THIS TIME. THE DEMO WORK HAS BEEN COMPLETED ON THE ADJACENT PROPERTY BUT HAS NOT BEEN DONE ON THE CIRCLE K STORE AT THIS TIME.