| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/26/2014 | ENGINEERING PRE-CONSTRUCTION | Approved | ||
| 11/20/2013 | ENGINEERING PRE-CONSTRUCTION | Continued | 1) POST A SIGNED COPY OF YOUR NOI AT THE ENTRANCE TO YOUR CONSTRUCTION SITE 2) IMPLEMENT YOUR SWPPP - INSTALL SEDIMENT CONTROLS ALONG THE EAST AND WEST PERIMETERS OF THE SITE, CONTROLS MAY BE CHANGED BASED ON SITE SPECIFICS 3) INSTALL A CONCRETE/MATERIALS WASH OUT WHEN APPLICABLE 4) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED PER YOUR PERMIT. 5) SWEEP UP TRACKED SOIL OFF ADJACENT ROADWAYS AS NEEDED 6) CALL FOR RE-INSPECTION FOR INSTALL APPROVAL |
|
| 11/14/2013 | ENGINEERING PRE-CONSTRUCTION | Correction Required | 1) AREA OF DISTURBANCE IS >1 AC THEREFORE THE SITE IS REQUIRED TO HAVE A STORM WATER PERMIT AND STORM WATER PLAN. 2) CONTRACTOR MUST IMPLEMENT YOUR STORM WATER PLAN 3) CALL FOR PRE-CONSTRUCTION MEETING PRIOR TO GRUBBING AND GRADING 4) PROVIDE YOUR ADEQ AUTHORIZATION NUMBER AND POST A SIGNED COPY AT THE ENTRANCE TO YOUR SITE. COMPLY BY 10 WORKING DAYS - NON COMPLIANCE WILL RESULT IN A NOTIFICATION OF ADEQ ( NON-COMPLIANCE WITH AZPDES) |
|
| 11/13/2013 | ENGINEERING PRE-CONSTRUCTION | Continued | ROUGH GRADING HAS STARTED, NO INSPECTION CALLED IN. CONTRACTOR MUST CALL IN FOR PRE-CON MEETING. | |
| 10/17/2013 | ENGINEERING PRE-CONSTRUCTION | Continued | 1) CONTRACTOR ROUGH GRADING THE PARCEL 2) NO SEDIMENT CONTROLS IN PLACE 3) NO PRE-CON CALLED IN 4) WILL MEET WITH SUPERINTENDENT |
|
| 09/19/2013 | ENGINEERING PRE-CONSTRUCTION | Continued | NO CONTACT AT THIS TIME, NO ACTIVITY | |
| 07/10/2013 | ENGINEERING PRE-CONSTRUCTION | Continued | NO ACTIVITY | |
| 01/29/2013 | ENGINEERING PRE-CONSTRUCTION | Continued | NO ACTIVITY ON SITE | |
| 01/02/2013 | ENGINEERING PRE-CONSTRUCTION | Continued | NO CONSTRUCTION AT THIS TIME | |
| 12/06/2012 | ENGINEERING PRE-CONSTRUCTION | Continued | NO GRADING ACTIVITY AT THIS TIME | |
| 07/03/2012 | ENGINEERING PRE-CONSTRUCTION | Continued | NO ACTIVITY | |
| 06/29/2012 | ENGINEERING PRE-CONSTRUCTION | Continued | NO CONSTRUCTION WORK AT THIS TIME. THE DEMO WORK HAS BEEN COMPLETED ON THE ADJACENT PROPERTY BUT HAS NOT BEEN DONE ON THE CIRCLE K STORE AT THIS TIME. | |
| 06/26/2012 | ENGINEERING PRE-CONSTRUCTION | Prior to Intermediates | REVISION #1, Revised water meter line only. Cosultant was notified there is a concern that the floodplain use permit (T11OT01564) was not completed. Consultant is advised to discuss with reviewer before commencement of construction to resolve outstanding drainage issues. | |
| 06/22/2012 | ENGINEERING PRE-CONSTRUCTION | Continued | NO CONSTRUCTION YET, DEMO WORK HAS BEEN COMPLETED | |
| 06/21/2012 | ENGINEERING PRE-CONSTRUCTION | Continued | DEMO WORK AT THIS TIME | |
| 05/01/2012 | ENGINEERING PRE-CONSTRUCTION | Continued | NO CHANGES | |
| 04/11/2012 | ENGINEERING PRE-CONSTRUCTION | Continued | NO ACTIVITY ON SITE | |
| 02/15/2012 | ENGINEERING PRE-CONSTRUCTION | Continued | NO CONTACT, DEMO WORK ONLY | |
| 02/10/2012 | ENGINEERING PRE-CONSTRUCTION | Continued | NO CONTACT |