Permit: T11BU00885

Parcel: 11105063G

Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Date Description Inspector Results Comments
11/02/2011 GRADING - INTERMEDIATE Approved
10/04/2011 GRADING - INTERMEDIATE Continued SITE IS PARTIALLY PAVED. HIGH POINT AT NORTH END RUNNING EAST TO WEST. STORM WATER SHOULD SHEET FLOW NORTH AND SOUTH INTO WATER HARVESTING AREAS AND WALL OPENINGS. SCUPPER TO BE INSTALLED AT SIDEWALK
NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
09/19/2011 GRADING - INTERMEDIATE Continued 1) MET WITH SUPERINTENDENT, DISCUSSED APPROVED DEVELOPMENT PLAN.
2) CONTRACTOR WILL CONSTRUCT A NEW PARING LOT WITH COVERED PARKING.
3) STORM WATER WILL BE SURFACED DRAINED INTO WATER HARVESTING AREAS AND WALL OPENINGS.
4) NO SWPP < 1 AC
5) ENSURE A CONCRETE WASH OUT IS AVAILABLE
6) ENSURE TRACK OUT IS SWEPT UP OFF OF PUBLIC ROADWAYS