Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
Permit Number - T11BU00620
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/01/2013 | GRADING - INTERMEDIATE | Approved | ||
04/10/2013 | GRADING - INTERMEDIATE | Continued | NO AVTIVITY AT THIS TIME. | |
03/26/2013 | GRADING - INTERMEDIATE | Approved | ||
03/12/2013 | GRADING - INTERMEDIATE | Continued | WORKING ON PARKING AREA ON SOUTH SIDE OF NEW BUILDING. | |
01/31/2013 | GRADING - INTERMEDIATE | Continued | WORKING ON PARKING AREA SOUTH OF NEW BUILDING. | |
01/25/2013 | GRADING - INTERMEDIATE | Continued | PAVING LAST PART OF NEW PARKING AREA SOUTH OF NEW BUILDING . | |
01/17/2013 | GRADING - INTERMEDIATE | Continued | WORKING ON GRADING SOUTH OF NEW BUILDING . | |
01/08/2013 | GRADING - INTERMEDIATE | Continued | WORKING ON CURBING ON SOUTH SIDE OF NEW BUILDING. | |
01/03/2013 | GRADING - INTERMEDIATE | Continued | INSALLING CURBING IN NEW PARKING AREA. | |
12/21/2012 | GRADING - INTERMEDIATE | Continued | STARTING GRADING WORK ON SOUTH OF NEW BUILDING. | |
12/07/2012 | GRADING - INTERMEDIATE | Continued | AREA UNDER HELI-PAD HAS BEEN OPEN BY CONTRACTOR. | |
11/26/2012 | GRADING - INTERMEDIATE | Continued | WORKING ON LANDSCPING ON SOUTH EAST SIDE OF BUILDING. | |
11/16/2012 | GRADING - INTERMEDIATE | Continued | WORKING ON LANDSCAPING ON SOUTH SIDE OF NEW BUILDING. | |
10/29/2012 | GRADING - INTERMEDIATE | Continued | FINAL COAT OF PAVING SOUTH OF ER. | |
10/26/2012 | GRADING - INTERMEDIATE | Continued | STARTED PAVING FRIST COAT FOR DRIVE AND PARKING AREA. | |
10/18/2012 | GRADING - INTERMEDIATE | Continued | WALKED PHASE #6 WITH LYLE WORKING ON CURB AND ROAD WAY SOUTH OF E.R. | |
10/10/2012 | GRADING - INTERMEDIATE | Continued | WORKING ON CURBING IN NEW ENTRANCE TO ER. | |
09/24/2012 | GRADING - INTERMEDIATE | Continued | I LOOKED AT ALL THE PIPE AND STRUCTURES THAT HAVE BEEN INSTALLED UNDERNEATH THE HELIPORT PAD. ENSURE THAT ALL OF THE INSTALLED LINES, AND STRUCTURES ARE PER THE APPROVED PLANS. IF THERE ARE ANY CHANGES TOO THE APPROVED PLANS PLEASE NOTIFY THE ENGINEER OF RECORD AND HAVE THESE APPROVED BY HIM AND OUR REVIEW STAFF BEFORE CONTINUING FORWARD WITH ANY OF THE WORK. | |
09/21/2012 | GRADING - INTERMEDIATE | Continued | STROM DRAIN WATER PIPING TO BUBBLER .ONLY OK PER DETAIL 10 ON PAGE C2.18. | |
09/17/2012 | GRADING - INTERMEDIATE | Continued | STRIPING IN CROSS WALK ON SOUTH EAST SIDE OF NEW PARKING LOT HAVE BEEN INSTALLED. SIGNS DOWN IN ADA SPACES. | |
09/11/2012 | GRADING - INTERMEDIATE | Continued | COMPLET STRIPING IN ADA PARKING. NORTH WEST END OF NEW PARKING AT CROSS WALK OVER 2% ADVISED CONTRACTOR NOT TO USE OUT OF ADA SPECS. | |
09/07/2012 | GRADING - INTERMEDIATE | Continued | WALKED NEW PARKING AREA WITH DAVE. WENT OVER STRIPING THAT IS NEEDED BEFORE OPENING WITH BORDERLAND. | |
08/30/2012 | GRADING - INTERMEDIATE | Continued | WALKED SITE WITH CONTRACTOR WENT OVER PHASING FOR NEW PARKING AREA ON SOUTH SIDE OF NEW BUILDING. | |
08/09/2012 | GRADING - INTERMEDIATE | Continued | WALKED NEW PARKING AREA SOUTH OF NEW BUILDING. | |
05/23/2012 | GRADING - INTERMEDIATE | Continued | MET THE DEVELOPER ON-SITE AND LOOKED AT THE PIPE AND BASIN BOTTOM THAT HAS BEEN PLACED ON THE SOUTHSIDE OF THE WEST PAVILIAN. THE BASE OF THE STRUCTURE WAS POURED THIS MORNING ANDTHE FORMING FOR THE WALLS WILL BE DONE TOMORROW. SEE SHEET NUMBER C2.16 AND LOOK AT DETAIL #13 FOR THE AREA THAT HAS BEEN INSPECTED ON THIS DATE. | |
05/22/2012 | GRADING - INTERMEDIATE | Continued | STOPPED BY AND LOOKED AT THE SITE, WAS UNABLE TO LOCATED THE CONTRACTOR AT 4:00. IT APPEARS THAT THEY HAVE BEEN WORKING AT INSTALLING PIPE IN THE AREA ON THE SOUTHSIDE OF THE WEST PAVILION. I WILL STOP BY THE SITE TOMORROW AND MEET WITH THE CREW TO DETERMINE WHAT WILL NEED TO BE INSPECTED DURING THE NEXT 2 WEEKS TILL MIKE RETURNS. | |
05/19/2012 | GRADING - INTERMEDIATE | Continued | CONTRACTOR WANTS TO FINAL GRADING PERMIT FOR EAST SIDE CONSTRUCTION. ENSURE APPROVED DRAWINGS MATCH WHAT WAS CONSRTUCTED ON SITE. PROVIDE A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD STATING THAT ALL SITE WORK AND STORM WATER DRAINAGE WAS CONSTRUCTED PER THE APPROVED PLANS. |
|
05/14/2012 | GRADING - INTERMEDIATE | Continued | NO CHANGES, NO STORM WATER CONCERNS AT THIS TIME | |
05/07/2012 | GRADING - INTERMEDIATE | Continued | MET WITH THE CONTRACTOR AND LOOKED OVER TWO AREAS OF THE SITE WHERE THEY WERE FORMING FOR A DROP INLET STRUCTURE AT THE Y INTERSECTION, PLACEMENT OF ROCK RIP RAP SOUTH OF THE ABOVE NOTED STRUCTURE, ALSO IN THE DRAINAGE CHANNEL WEST OF THE RETENTION/ DETENTION BASIN WEIR OUTLET SOUTH OF THE PARKING GARAGE. MIKE RUSSO WILL CHECK IN WITH THIS CREW ONCE HE RETURNS ON 5/10/2012. | |
05/01/2012 | GRADING - INTERMEDIATE | Continued | 1) TOOK PICTURES OF RE-BAR LAY OUT FOR CATCH BASIN INSTALLATION ALONG RING ROAD AT CHANNEL CROSSING , NW SIDE OF SITE. OK FOR CONCRETE (FLOOR). 2) NO STORMWATER CONCERNS AT THIS TIME. |
|
03/29/2012 | GRADING - INTERMEDIATE | Continued | INSPECTED THE HEADWALL FORMS LOCATED AT THE STORM WATER CHANNEL ROAD CROSSING. FORMS OK ALONG NORTH SIDE OF CROSSING. AWAITING CONCRETE, TOOK PICS. NO STORM WATER CONCERNS |
|
03/27/2012 | GRADING - INTERMEDIATE | Continued | INSPECTED COMPLETED CATCH BASINS. LOOKED AT FORMS AND RE-BAR FOR HEADWALL AT CHANNEL CROSSING |
|
03/19/2012 | GRADING - INTERMEDIATE | Continued | VISITED SITE, CONTRACTOR STILL WORKING ON CHANNEL CROSSING AT RING ROAD, HEADWALL AND ROCK RIP RAP NOT IN PLACE. CONTRACTOR STILL WORKING ON CATCH BASIN AND STORM DRAIN TIE-IN ALONG NE CORNER OF SITE. NO STORM WATER CONCERNS AT THIS TIME. |
|
03/15/2012 | GRADING - INTERMEDIATE | Continued | T09BU01354 1) WALKED PARKING AREA AND PEDESTRIAN ACCESS, OUTSIDE NEW PARKING GARAGE - PROPOSED OCCUPANCY IS FOR APRIL 24. 2) MOST LANDSCAPING AND STORM DRAINAGE WILL BE COMPLETED NEAR THE PARKING AREA. 3) TEMP VEHICLE AND ACCESS WILL BE IN PLACE W/ SIGNAGE. 4) ENSURE FENCING AND/OR BARRIERS ARE INSTALLED TO SEPARATE THE PUBLIC FROM CONSTRUCTION. 5) AWAITING FORMS AND CONCRETE FOR HEADWALLS AT ROAD CROSSING ALONG WEST CHANNEL. PERMIT# T11BU00620 6) CONTRACTOR POURED THE 1x2 PIPE TRANSITION CATCH BASIN ALONG THE NE CORNER OF THE SITE. 7) THE TWO CATCH BASINS ALONG THE SOUTH SIDE OF THE RING ROAD, HAVE BEEN FORMED. ONE BASIN TIES INTO EXISTING RCP. THE OTHER BASIN DROPS INTO AN HDPE STORM PIPE WICH TIES INTO THE EXISTING RCP TRUNK LINE. 8) THE APPROVED PLAN CHANGE TO THE SLOTTED DRAIN ALONG THE FLOW LINE OF THE RING ROAD, HAS NOT BEEN CONSTRUCTED. THE CHANGE WILL INCLUDE A VALLEY GUTTER AND SMALL CATCH BASIN. 9) NO STORM WATER CONCERNS AT THIS TIME. |
|
02/06/2012 | GRADING - INTERMEDIATE | Continued | INSPECTED MANHOLE THAT WAS POURED FOR THE STORM DRAIN LINE TRANSITION AT THE WEST SIDE OF THE NEW PARKING GARAGE. THE CONTRACTOR TOOK PICS IN ORDER TO DOCUMENT THE MANHOLE CONSTRUCTION. NO STORM WATER CONCERNS AT THIS TIME |
|
01/26/2012 | GRADING - INTERMEDIATE | Continued | 1) APPROXIMATELY 150 ' OF 18" PVC STORM PIPE WAS INSTALLED FROM THE WEST SIDE OF THE NEW PARKING STRUCTURE ROOF DRAINS. 2) A TRANSITON/ MANHOLE WILL BE INSTALLED FROM 16" PVC TO 18" PVC SDR 35. 3) STORM PIPE WILL TERMINATE INTO A BUBBLER BOX SHOWN ON APPROVED PLANS. 4) ENSURE ANY SIGNIFICANT CHANGES IN SITE WORK FROM THE ORIGINAL APPROVED PLAN MUST BE APPROVED BY THE CITY OF TUCSON. |
|
01/10/2012 | GRADING - INTERMEDIATE | Continued | 1) INSPECTED INSTALL OF STORM DRAIN PIPING ALONG RING ROAD/CORRIGATED PLASTIC PIPE. TRENCH WAS COMPACTED, PIPE WAS BEDDED AND GRADED TO DRAIN PER APPROVED PLAN. AMOUNT OF PIPE INSTALLED WAS CHANGED/SEE REVISED PLAN. 2) INSPECTED PREPARATION OF CATCH BASIN INSTALL AT EAST END OF RING ROAD AT CROSSING. CHANGED FROM 1 SRP STORM DRAIN TO TWO SMALLER PIPES. 3) NO STORM WATER CONCERNS AT THIS TIME. 4) NEED CITY APPROVAL FOR BOTH CHANGES |
|
11/18/2011 | GRADING - INTERMEDIATE | Continued | 1) INSPECTED CULVERT CROSSING AT CHILLER PLANT ALONG NORTH SIDE OF HOSPITAL. PIPE HAS BEEN INSTALLED PER PLAN. 2) INSPECTED NEW PARKING AREA ALONG NORTH SIDE OF HOSPITAL. PARKING AREA CONSTRUCTED PER APPROVED PLANS. 3) CONTRACTOR PREPING AREA ALONG NE CORNER OF SITE FOR DRAINAGE IMPROVEMENTS AND ROAD EXPANSION. 4) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. |
|
11/10/2011 | GRADING - INTERMEDIATE | Continued | 1) BUBBLER BOX HAS BEEN INSTALLED, PICTURES TAKEN TO SHOW LATERAL LINE CONNECTION AND DEPTH OF BOX. FILTER FABRIC AND ROCK PLACED IN BOTTOM OF BOX. 2) CONTRACTOR WORKING ON INSTALLATION OF STORM DRAIN RCP AT RING ROAD CROSSING ALONG NORTH SIDE OF COMPLEX. PIPE WILL DRAINAGE CHANNEL NEXT TO ROAD AND NEW PARKING LOT. ENSURE PIPE IS INSTALLED PER THE APPROVED PLANS AND COT STD SPECS FOR PUBLIC IMPROVEMENTS. 3) CONTRACTOR WORKING ON PARKING LOT AT NORTH SIDE OF SITE. ENSURE LOT IS COMPLETED PER THE APPROVED PLAN PRIOR TO OCCUPANCY. 4) SEDIMENT CONTROLS IN PLACE, NO STORM WATER CONCERNS AT THIS TIME. 5) CONTRACTOR WILL BE WORKING ON INSTALL OF STORM DRAINAGE ALONG FAR NE CORNER OF SITE NEXT WEEK. |
|
11/04/2011 | GRADING - INTERMEDIATE | Continued | WALKED SITE WITH SUPERINTENDENT, DISCUSSED PARKING AREA BEING RE-PAVED AND FINISHING WORK AT ROOF DRAIN/STORM DRAIN PIPING AND BUBBLER BOX. NO CONCERNS AT THIS TIME. | |
11/02/2011 | GRADING - INTERMEDIATE | Continued | SITE FOLLOW UP. NO STORM WATER CONCERNS AT THIS TIME. | |
11/01/2011 | GRADING - INTERMEDIATE | Continued | 1) FLOOR OF CATCH BASINS POURED - 8" BASIN WALLS BEING CONSTRUCTED FOR WEST MOST BASIN. 2) AWAITING MATERIALS FOR INSTALLATION OF BUBBLER BOX. 3) MANHOLE TOP INSTALLED AT GRADE. 4) BUILDING PAD AT FINISH GRADE ELEV. 5) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
|
10/28/2011 | GRADING - INTERMEDIATE | Continued | STORM DRAIN LINE HAS BEEN COVERED AWAITING BUBBLER BOX. MANHOLE AND CATCH BASINS NEED FINISHING. NEED TO SWEEP UP TRACKING OFF OF PUBLIC ROADWAYS |
|
10/27/2011 | GRADING - INTERMEDIATE | Continued | 1) CONTRACTOR IN PROCESS OF INSTALLING 20 LF OF 10" SDR 35 AND 62 LF OF 6" SDR 35 ALONG THE SOUTH SIDE OF THE SITE. 2) MANHOLE HAS BEEN POURED FOR PIPE TRANSITION. 3) ONE CATCH BASIN HAS BEEN FORMED W/ #4 REBAR CAGE. CATCH BASIN WILL BE A TRANSITION FROM 10" TO 6" SDR 35 AND OUTLET OF EXISTING CORREGATED STEEL PIPE. 4) HOLE HAS BEEN PREPED FOR THE 18" ABS BUBBLER BOX TO BE INSTALLED AS A BRANCH OFF THE 6" SDR 35 LINE. ENSURE THE GRAVEL PACK IS INSTALLED IN THE BOTTOM OF THE BOX PER THE APPROVED PLANS. 5) TWO MORE CATCH BASINS TO BE INSTALLED ALONG THIS SECTION OF PIPE TO INCLUDE A 15" STUB OUT CONNECTED TO THE ROOF DRAIN OF THE NEW BLDG. 6) TRENCH HAS BEEN COMPACTED AND BEDDED FOR PIPE., 7) OK TO COVER. 8) SIGNIFICANT AMOUNTS OF TRACKING HAVE BEEN OBSERVER AT GLENN AND AT CRAYCROFT FROM CONSTRUCTION EQUIPMENT TRAFFIC. ENSURE ALL PUBLIC ROADWAYS ARE SWEPT MORE OFTEN TO REDUCE THE AMOUNT OF TRACKING. |
|
10/26/2011 | GRADING - INTERMEDIATE | Continued | CHECKED PROGRESS ON INSTALL OF STORM DRAIN LINE FOR ROOF DRAINS OF NEW BLDG. CONTRACTOR IS CONSTRUCTING MANHOLE FOR MAINT ACCESS AT PIPE TRANSITION. SCHD 40 PVC USED UNDER BLDG FOUNDATION AND SDR 35 FOR THE REMAINING PIPE. DUE TO THE FACT THAT THE PIPE RUN BETWEEN MANHOLE AND CATCH BASIN IS SO SHORT (60') NO LOCATOR TAPE IS NEEDED. FORMED MANHOLE #6 RE-BAR/90 DEG TRANSITION, PIPES CUT AT STRAIGHT EDGE. SWEEP UP TRACKING OFF ROADWAYS, NO OTHER SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
|
10/25/2011 | GRADING - INTERMEDIATE | Continued | CONTRACTOR INSTALLING STORM DRAIN PIPING CONNECTED TO ROOF DRAINS. SCHEDULE 40 PVC BEING USED UNDER THE BLDG AND PIPE WAS PRESSURE TESTED. PIPING BEIN INSTALLED UNDER AND ALONG BLDG EXTENTION. WILL CHECK TO SEE IF TRACER WIRE IS REQUIRED. NO STORM WATER CONCERNS AT THIS TIME |
|
10/14/2011 | GRADING - INTERMEDIATE | Continued | SITE FOLLOW-UP TO LOOK AT EXISTING STORM DRAIN TO NEW STORM DRAIN TIE-IN. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
|
10/12/2011 | GRADING - INTERMEDIATE | Continued | CONSTRUCTION WILL TAKE PLACE AT MULTIPLE SITES. TREVEN W/BORDERLAND STATED THAT TEMP SEDIMENT CONTROLS WILL BE INSTALLED AT EACH SITE AS CONSTRUCTION TAKES PLACE. THE OVERALL PROJECT WILL BE SEPARATED INTO SEVEN PHASES. SITE A = ADDITION TO EXISTING BLDG (BORDERLAND) 1) PERIMETER SEDIMENT CONTROLS HAVE BEEN INSTALLED ALONG THE EAST AND NORTH SIDES. 2) RE-ESTABLISH ROCK ENTRANCE/EXIT 3) SWEEP TRACKING 4) DOCUMENT STORM WATER SELF INSPECTIONS. SITE B = NEW MULTI STORY PARKING GARAGE. (J AND D CONS) 1) PERIMETER SEDIMENT CONTROLS HAVE BEEN INSTALLED ALONG WEST AND SOUTH SIDES. 2) ROCK ENTRANCE/EXIT IN PLACE 3) SWEEP TRACKING 4) ENSURE STORM WATER SELF INSPECTIONS ARE COMPLETED AND DOCUMENTED |