Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 08/20/2012 |
GRADING - INTERMEDIATE |
|
Approved |
|
| 07/19/2012 |
GRADING - INTERMEDIATE |
|
Continued |
SITE WORK AND LANDSCAPING NOT COMPLETED FOR BOTH SITES. |
| 05/18/2012 |
GRADING - INTERMEDIATE |
|
Continued |
NO CONCERNS AT THIS TIME. |
| 05/08/2012 |
GRADING - INTERMEDIATE |
|
Continued |
NORTH SIDE PARKING LOT HAS BEEN PAVED AND STRIPED. |
| 04/30/2012 |
GRADING - INTERMEDIATE |
|
Continued |
WORKING ON NORTH WEST PARKING AREA. |
| 04/05/2012 |
GRADING - INTERMEDIATE |
|
Continued |
WORKING ON CURBING ON NORTH SIDE OF BUILDING. |
| 03/14/2012 |
GRADING - INTERMEDIATE |
|
Continued |
WORKING ON SOUTH SIDE BUS DROP OFF. |
| 03/02/2012 |
GRADING - INTERMEDIATE |
|
Continued |
WORKING ON PAVING AND CURBS ON EAST SIDE AND AB ON SOUTH SIDE. |
| 01/19/2012 |
GRADING - INTERMEDIATE |
|
Continued |
30" SRD IN TO RETENTION BASIN #1 OK |
| 10/13/2011 |
GRADING - INTERMEDIATE |
|
Continued |
CREWS WORKING ON DIGGING FOR THE UTILITY INSTALLATIONS, AND FOOTER EXCAVATION ON THE NORTHERN QUADRANTS OF THE SITE, ROADWAY EXCAVATION ALONG THE EAST SIDE OF THE SITE. |
| 09/19/2011 |
GRADING - INTERMEDIATE |
|
Continued |
SITE APPEARS TO BE WORKING OKAY AT THIS TIME. I AM DRIVING THROUGH ALL THE SITE TO SEE THAT THEY HAVE NOT DRASTICALLY CHANGED DURING MY RECENT ABSENCE. THIS SITE WILL BE INSPECTED IN THE NEAR FUTURE DEEPER IN DEPTH TO ENSURE COMPLIANCE. |
| 08/03/2011 |
GRADING - INTERMEDIATE |
|
Continued |
LOOKED OVER THE SITE WORK HAS ALREADY BEEN STARTED ON THE EXCAVATION AND THE GRADE PREPARATION OF THE SITE. THIS SITE WILL BE CHECKED MORE ON FRIDAY WHILE THE CONTRACTOR IS STILL WORKING TO ENSURE WHAT IS HAPPENING AT THIS TIME. |