Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/18/2011 | FIRE SPKLR - FINAL | Approved | ||
| 09/27/2011 | FIRE SPKLR - FINAL | Partial Approval | Fire pump passed final test, still need the following: 1. Revisions will be required to the original permit to include details of the mechanical room. These include but are not limited to: Details for walls ect. Electrical including pump controls Heat for pump room per NFPA 20 Drain for the pump room per NFPA 20 Model and serial numbers for jockey and fire pumps 2. Placement of all piping, valves normally open or closed. 3. All tampers and flows 4. Rewire plug for block heater, electrical cord to short. 5. Need copy of pump test (flows and table) |
|
| 09/09/2011 | FIRE SPKLR - FINAL | Denied | Pump test required. | |
| 09/07/2011 | FIRE SPKLR - FINAL | Cancelled | IVRS - RI canceled |