Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - TIER REV
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/21/2011 | GRADING - TIER REV | Approved | AN APPROVED REVISION WAS COMPLTED AND AVAILABLE ON SITE. THE PLAN SHOWED ALL CHANGES THAT WERE MADE | |
| 05/25/2011 | GRADING - TIER REV | Continued | COMPLET LIST FROM 5-13-2011. GRADING ON SOUTH SIDE PROJECT PRIVDE AP PLANS PER NOTES FROM 5-13-2011 | |
| 05/13/2011 | GRADING - TIER REV | Continued | 1) CONTRACTOR/OWNER CHANGED FROM ASPHALT TO CONCRETE ON HALF THE PROJECT. 2) CONTRACTOR/OWNER CHANGED DIRECTION OF SURFACE FLOW FROM NW CORNER INTO A 3" PVC PIPE TO THE NE CORNER.-NEED REVISED/APPROVED PLANS 3) CONTRACTOR WANTS TO REMOVE A PORTION OF THE WEDGE CURB IN THE ROW IN ORDER TO GAIN 6" IN GRADING THE PARKING AREA TO DRAIN.- NEED ROW PERMIT 4) PRIOR TO FINAL PROVIDE A REVISED PLAN AND BUILD THE SITE PER PLAN. |
|
| 05/12/2011 | GRADING - TIER REV | Cancelled |