Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING PRE-CONSTRUCTION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/21/2011 | ENGINEERING PRE-CONSTRUCTION | Approved | ||
| 05/13/2011 | ENGINEERING PRE-CONSTRUCTION | Continued | 1) CONTRACTOR/OWNER CHANGED FROM ASPHALT TO CONCRETE ON HALF THE PROJECT. 2) CONTRACTOR/OWNER CHANGED DIRECTION OF SURFACE FLOW FROM NW CORNER INTO A 3" PVC PIPE TO THE NE CORNER.-NEED REVISED/APPROVED PLANS 3) CONTRACTOR WANTS TO REMOVE A PORTION OF THE WEDGE CURB IN THE ROW IN ORDER TO GAIN 6" IN GRADING THE PARKING AREA TO DRAIN.- NEED ROW PERMIT 4) PRIOR TO FINAL PROVIDE A REVISED PLAN AND BUILD THE SITE PER PLAN. |
|
| 05/12/2011 | ENGINEERING PRE-CONSTRUCTION | Cancelled | NO CONTACT, NO ONE ON SITE, BLDG LOCKED |