Inspection Status: Approved
Inspection History: STORMWATER INSTALL OF CONTROLS
| Date |
Description |
Inspector |
Results |
Comments |
| 08/17/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Approved |
|
| 06/09/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Partial Approval |
PROVIDE LETTER FOR 8" SDR 35 NOT 12" sdr 35 8" |
| 05/09/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Continued |
NO CONCERNS AT THIS TIME. |
| 05/02/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Continued |
SWPPP OK AT THIS TIME. |
| 04/25/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Continued |
DAR-HILL TO INSTALL SWPPP ON 4-25-2011 PER SHANNON. |
| 04/21/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Continued |
Controls not in place at time of pre-con, told contractor that they need to be installed ASAP. |