Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/23/2010 | PLUMBING - FINAL | Approved | IVRS - Inspection :* | |
| 11/17/2010 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) TEST TO HOLD FOR 15 MINUTES WITH NO LOSS OF PRESSURE |
|
| 11/15/2010 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) PROVIDE TEST GAUGE IN 1/10 INCREMENTS 2) TEST TO BE MINIMUM 10 PSI AT TIME OF INSPECTION 3) VALVES TO BE LISTED FOR GAS USE 4) PIPING TO BE SUPPORTED AND SEALED AT BLDG ENTRANCE AND AT CORRECT INTERVALS 5) ALL VENTING CONNECTIONS FOR FURNACES TO BE MADE UP COTRRECTLY, SECURED PROPERLY WITH FASTENERS 6) PROVIDE BONDING OF BLDG GAS SYSTEM 7) PROVIDE ACCESS TO ROOF FOR VENT TERMINATION 8) NO TAPE ON VENT CONNECTION |