Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/11/2011 | PLUMBING - FINAL | Approved | IVRS - Inspection :* | |
| 09/19/2011 | PLUMBING - FINAL | Partial Approval | IVRS - Inspection :* 1) PROVIDE MINIMUM 1" CLEARANCE TO COMBUSTIBLES FROM FURNACE FLUE PIPE |
|
| 09/01/2011 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) GAS CLEARANCE LEFT 2) READ NOTE #4 THIS SHEET AND COMPLY |
|
| 08/25/2011 | PLUMBING - FINAL | Not ready for Inspection | 1. PROVIDE MINIMUM 1- PSI TEST ON ENTIRE SYSTEM BECAUSE OF TIME BETWEEN INSPECTIONS. 2. BOND TO COLD WATER PIPE 3. MAKE UP WATER HEATER VENT CONNECTION AT UPPER 45 DEG TURN UP TOWARDS ROOF IN WATER HEATER CLOSET CORRECTLY. 4. FURNACE VENT TO BE EXTENDED THROUGH ROOF FLASHING WITH DOUBLE WALL VENT PIPING TO 3' ABOVE COOLER INTAKE AND HAVE APPROVED VENT CAP. PROPERLY FLASH THIS VENT THROUGH ROOF & EXTEND WATER HEATER VENT WITH DOUBLE WALL VENT PIPING TO 3' ABOVE COOLER INTAKE. |
|
| 10/26/2010 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) PROVIDE BOND FOR GAS PIPING AND COMPLETE #2 OF LIST 10/20/10 2) COMPLETE AND CALL BACK FOR FINAL |
|
| 10/20/2010 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) EXTEND FLUE VENT FOR WATER HEATER 3' COOLER AND TYPE B CAP 2) RUN T & P TO DAYLIGHT 3) PROVIDE CSA APPROVED VALVES FOR WAER HEATER AND FURNACE 4) PROVIDE APPROVED INSTALL OF FLUE VENT FOR WATER HEATER AND FURNACE 5) TEST NOT HOLDING-REPAIR LEAKS |