| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/04/2011 | SITE - SEWER | Approved | IVRS - Inspection :* | |
| 02/17/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
| 02/16/2011 | SITE - SEWER | Cancelled | IVRS - RI canceled | |
| 11/29/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) PROVIDE TESTING ON PIPING FROM MANHOLE #1 EXISTING MANHOLE TO COMPLETE TESTING |
|
| 11/23/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) MANHOLE #1, 2, 3 & 4 TEST OK 2) 8" PIPING FROM MANHOLE #4 TO 3 TEST OK AND 8" FROM MANHOLE #1 & 2 3) DIP PIPING FROM MANHOLE #2 TO 3 OK OK 4) MANHOLE #4 4" PIPING TO BLDG #1,7 & 6 OK 5) MANHOLE #3 4' PIPING TO BLDG AND #5 OK 6) MANHOLE #2 4" PIPING TO BLDG #4 & 3 OK 7) PIPING TO BLDG #2 NOT HOLDING TEST REPAIR |
|
| 11/19/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) PER HIGH LIGHT ON APPROVED PLAN |
|
| 11/18/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :*PER HIGH LIGHTS ON PAGE C.6 | |
| 11/17/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) PER HIGHLIGHT ON PAGE C.6 OF APPROVED SITE PLAN |
|
| 11/16/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) PER HIGHLIGHT ON APPROVED PLANS |
|
| 11/15/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) 8" STUB DOWN STREAM FROM MH #1 ? UPSTREAM TO MH #2 2) 2-4" STUBS AND 8" D.I. CONTINOUS FROM MH #2 TO MH #3, 2-4" STUBS AND 8" SDR CONTINUES APP. 40' UPSTREAM TOWARD MH #4 3) BEDDING, LAYING, TRACER WIRE, SHADING, BACK FILLING 4) ALL TESTING AT LATER DATE BY COT AND RICK ENGINEERING PER HIGHLIGHT C-6 5) BASES POURED MH #1,2 & 3 |