Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/01/2010 | PLUMBING - GAS PRESSURE TEST | Approved | ||
| 03/30/2010 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* 1) 15 PSI TEST APPEARS TO BE HOLDING AND CONNECTION TO EXISTING OK 2) OK TO POUR LEVEL CONCRETE BASE AND PROTECT PIPING PASSING THRU CONCRETE 3) OK TO SET WATER HEATER 4) SUPPORT PIPING |
|
| 03/24/2010 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* |
|
| 03/22/2010 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* |