Inspection History Details
Inspection Status: Not ready for Inspection
Inspection History: SIGN SITE REVIEW
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/15/2016 | SIGN SITE REVIEW | Not ready for Inspection | PULLED UP AND PRINTED THE INFORMATION FOR THIS PERMIT AND FOR THE VIOLATION #T15DV03727 AND TOOK IT OUT TO THE SITE MANAGER. SHE WILL BE SENDING IT TO THE COORPORATE OFFICE FOR THEIR REVIEW. I WILL SET UP AN INSPECTION TO BE PERFORMED BY RICARDO MORENO ON 9/19/2016 TO SEE IF WHAT THEY HAVE THERE AT THIS TIME IS ACCEPTABLE. IF THE SITE IS IN NON-COMPLIANCE STATUS WE WILL ADVISE THE SITE MANAGER AND ASK THAT SHE CONTACT THE COORPORATE OFFICE. IF IT IS FOUND UNACCEPTABLE AT THAT TIME BRIAN WIESE WILL ADVISE US WHAT TO DO. | |
| 09/14/2016 | SIGN SITE REVIEW | Not ready for Inspection | WENT BY THE SITE TO SEE WHAT TYPE OF WORK HAS BEEN PERFORMED AND IF IT IS COMPLETE AT THIS TIME. THE PERSONNEL ONSITE WILL CONTACT THE OWNER OF THE SITE AND ASK IF THE I CAN BE INSPECTED AT A LATER DATE. | |
| 08/31/2016 | SIGN SITE REVIEW | Not ready for Inspection | THIS IS TO REOPEN THE PERMIT SO DAVE ROBERTS CAN PERFORM AN ELECTRICAL INSPECTION ON THE SIGNS. | |
| 10/06/2010 | SIGN SITE REVIEW | Denied | PRINTING TOO SMALL, NEEDS TO BE LEGIBLE; CAN'T READ 1. "TYPICAL DETAIL CHANNEL LETTER" 2. PROVIDE VOLTAGE, CURRENT OF SIGN 3. WILL EXISTING CURCUIT BE USED OR NEW ONE INSTALLED? |
|
| 10/04/2010 | SIGN SITE REVIEW | Partial Approval | SITE OK; PENDING ELEC & SIGN REVIEW |