Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/10/2010 | MECHANICAL - FINAL | Approved | IVRS - Inspection :* | |
| 09/07/2010 | MECHANICAL - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) RTU LINE SETS TO BE COATED 2) PROVIDE SERVICE OUTLET AT RTU'S WITHIN 25' 3) CONDENSATE NOT PROPERLY INSTALLED 4) FLUE PIPE NOT PROPERLY INSTALLED 5) NO CONDENSATE ON HARD SURFACE 6) PROVIDE 36" CLEARANCE AT DISCONNECT 7) PROVIDE ROOF JACKS AT ALL ROOF PENETRATIONS 8) PACKAGE UNIT OVER FUSED 9) ALL WORK TO BE COMPLETE OR A REFEE WILL BE ISSUED |
|
| 09/01/2010 | MECHANICAL - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) CONDENSATE CANNOT TERMINATE ONTO A SIDE WALK /PATIO 2) FURNACE VENT CONNECTOR-SOME FITTINGS ARE BACKWARDS 3) INSPECTION STOPPED 4) CORRECTIONS TO NUMEROUS TO LIST 5) CONTRACTOR MUST BE HERE FOR NEXT INSPECTION 6) PROVIDE ACCESS TO ROOF |
|
| 08/27/2010 | MECHANICAL - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) PROVIDE ACCESS TO ROOFS 2) PROVIDE PROPER DESCRIPTION OF WORK |