Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/05/2010 | MECHANICAL - FINAL | Approved | IVRS - Inspection :* 1) CORRECTIONS HAVE BEEN MADE |
|
| 01/29/2010 | MECHANICAL - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) TERMINATE CONDENSATE WITHIN 6" OF THE GROUND 2) PAINT EXPOSED PVC WITH LATEX PAINT 3) RELOCATE GAS LINE FROM BLOCKING ACCESS AND REMOVED OF COMPRESSOR 4) NEED TO SEE ALL NEW GAS PIPING 5) PROVIDE A PRESSURE TEST ON ALL NEW GAS PIPING 6) PROPERLY SUPPORT GAS PIPE ON ROOF AFTER RELOCATING 7) PROVIDE A BUSING IN ELECTRIC DISCONNECT-NOT TAPE 8) SECURE THE ANGLE IRON STAND TO THE STRUCTURE 9) PROVIDE THE REQUIRED GFI SERVICE RECEPT ON THE ROOF 10) PROVIDE THE REQUIRED STRUCTURAL DRAWING AND APPROVAL FOR NEW EQUIPMENT ON ROOF |