| 05/28/2015 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
Closed; dilapidated portions of structure abated and/or demolished; permit remains issued. |
| 10/23/2014 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
No further progress. Unit 1 rehabbed, but lacks HVAC; unit 2 demo'd. Contractor has not done any work under permit. |
| 09/12/2014 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
No further work, see court hearing. |
| 06/06/2014 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
Refuse from demo removed at location. Temp elec service inspection on 06/05/14, approved. TEP can bring power into main service panel Schedule will be provided once owner arranges with TEP. Unit 1 is receiving finish on doors, trim and paint; with electrial being finished. |
| 04/29/2014 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
No change; no inspections, no visible work at site. |
| 04/14/2014 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
No change; no inspections, no visible work at site. |
| 02/27/2014 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
No change. |
| 02/07/2014 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
No inspections or plan revisions since last inspection 12/17/14 on permit T12CM00162; site inspection showed a demolition of the dilapidated portion of "unit 2" has occurred. |
| 12/17/2013 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
Unit 1 has received drywall installation and inspections; demo continuing on portions of unit 2; addressing issue with TEP resolved, which will allow for further inspections, starting with electrical on unit 1. |
| 10/17/2013 |
INSP - FOLLOW UP CODE ENFORCE |
|
Court Inspection |
Site inspection; further progress on unit one w/ approved electrical; drywall installation and inspection upcoming. Plans for unit 1 resubmitted and approved; unit 2 alterations to roof being formulated; plans will be submitted in next few week. Roof top HVAC unit will be used in lieu of mini-splits. |
| 08/08/2013 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
On site w/ TW; 2 person crew on site cleaning debris from unit 2; unit 1 remains in similar condition as from 11/02/13; almost complete, requires finishing work and inspections. Unit 2 not started and remains highly dilapidated. Notes on permit inspection from Nov. 2012 required resubmittals for changes to mechanical system and lack of plumbing plan, changes to service diagram; it also noted bathroom exhaust/fan and to secure/terminate home runs at sub panel. These items have not been done, submitted, or inspected 8 months later. |
| 05/07/2013 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
No compliance; no active work at location. Windows installed on unit 1. Photos in Sire. Permit expires 5/13/13; plans not submitted as previously indicated, no inspections since November. |
| 11/02/2012 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
Site inspection on front unit progress; work completed and ready for inspections; finishing work can be done after approvals. Contractor expects inspections on Mon or tues. |
| 08/24/2012 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
Work is progressing at site to include framing, etc. No inspections on permit. |
| 06/12/2012 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
No compliance; no action on permit, no active work at location. |
| 01/12/2012 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
No compliance; demolition on hold. |
| 06/16/2011 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
No compliance; no work has been done. No permit on file. |
| 05/18/2011 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
No compliance; no work has been done on property; no permits have been issued. |
| 01/18/2011 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
No compliance; no work has been done on property; no permits have been issued. Some vegetation removed, but not all. Scattered refuse remains on property. Application for CDBG grant has not been submitted. |