Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/10/2011 | PLUMBING - INTERMEDIATE | Approved | ||
| 11/03/2011 | PLUMBING - INTERMEDIATE | Partial Approval | NEED TO SEE TEST ON GARAGE SUMPS | |
| 10/11/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 09/29/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) DWV, DOMESTIC WATER AHD RO TO COFFEE 273 WITH WATER HEATER IN MECH 1 208 OK |
|
| 09/13/2011 | PLUMBING - INTERMEDIATE | Partial Approval | LEVEL 2 - DOMESTIC AND RO ABOVE CEILING. STILL NEED TO SEE W.H. TIE IN @ MECH ROOM | |
| 08/23/2011 | PLUMBING - INTERMEDIATE | Denied | 3 COMPARTMENT SINK IN PANTRY 261 REQUIRES DIRECT CONNECTION TO DRAINS AS PER APPROVED PLANS. | |
| 08/23/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* L-9 FUTURE 3" W/CONNECTON TO STACK 8-OK RM.959 SINK DWV AND WATERS OK L-3 RM 340 P-15 W/ TEST OK L-2 RM 273 OFFICE WALLS ONLY. PANTRY REVENT OF FS OK. STILL NEED CORRECT 3 COMP SINK DRAIN. HARD LID IN HALL AT STR 6 OK. HOW WILL YOU SEAL THE CONECTION BETWEEN TILED RAISED FLOOR AND YOUR FLOOR SINKS? A FLANGED FIXTURE WOULD BE APPROPRIATE FOR A WATER SISAL CONNECTION. HAVE YOU INSTALLED THE WRONG SINK? |
|
| 08/18/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) BR #256 DWV, DOMESTIC AND ? WATER INWALLS ONLY OK. RECALL FOR COMPLETION ON WASTE AND VENT 2) BR #246 IN WALL OK, RECALL FOR WASTE INSPECTION |
|
| 08/15/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) BR SINK PIPING IN WALLS ROOM #371 TEST OK 2) ROOM #351 DWV TEST IN WALLS OK 3) LEVEL 9 ROOM 932 FUTURE 3" DWV BELOW FLOOR OK 4) ROOM #959 SINK IN WALLS AND WATER PIPING OVERHEAD TO TIE IN |
|
| 08/01/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) DWV LEVEL 9 BR SINK IN WALLS AND ABOVE CEILING OK, INSTALL MISSING SAFETY PLATES 2) DOMESTIC AND RO PIPING LOOKS GOOD, NOT YET UNDER TEST (EAST BREAK ROOMS) |
|
| 07/29/2011 | PLUMBING - INTERMEDIATE | Partial Approval | LEVEL 9 WEST DWV AND POTABLE AIR TEST 5 PSI OK. OK TO COVER WALLS | |
| 07/22/2011 | PLUMBING - INTERMEDIATE | Partial Approval | LVLS 4 - 8 1/2" RO & CW FROM EAST MECH TO BREAK ROOM | |
| 07/20/2011 | PLUMBING - INTERMEDIATE | Partial Approval | NEED TEST ON VENT EAST LVL 9 (FUTURE STUB OUT) | |
| 07/15/2011 | PLUMBING - INTERMEDIATE | Partial Approval | RELOCATE STUBOUTS ON LEVEL 4 OK | |
| 07/13/2011 | PLUMBING - INTERMEDIATE | Partial Approval | RELOCATION OF 3" DRAIN STUB AT RESTROOM CORE LEVELS 5-9 OK. 4 NOT READY | |
| 06/29/2011 | PLUMBING - INTERMEDIATE | Partial Approval | RELOCATION OF 3" STUB OUT ON DWV ABOVE CIELING LEVEL 6 & 9 OK. NEED TO UNCOVER 5 AND REWORK 7. | |
| 04/22/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 04/18/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | 4/18/11 NOTHING READY PER ROB 4/20/11 CPVC IN WALL, LEVELS 4-8, WEST BR SINK, TEST OK. SECURE PIPING AS PREVIOUSLY REQUESTED. DOMESTIC WATER IN WALL AT BR SINK, LEVEL 8 TEST OK. INSULATE DOMESTIC HW, ALL LEVELS |
|
| 04/14/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | DO NOT TEST CPVC WITH AIR, TEST HYDROSTATICALLY, BLEED ALL AIR FROM LINE. PUTTING AN INSPECTORS SAFETY AT RISK WILL INCUR FEES. SECURE CPVC RO PIPING |
|
| 04/07/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) FAMILY RR #444 AND BR 463 SINK; DWV AND DOMESTIC WATER TEST OK |
|
| 04/06/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* |