Date Description Inspector Results Comments
03/15/2011 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
1) CMU WALL COMPLETE TO TOP OUT
03/10/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) TOP OUT (2ND LIFT) AT BALANCE OF NORTH CMU WALL AND 1ST LIFT AT EAST AND SOUTH CMU WALL OK
03/07/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) EAST 1/3 OF NORTH WALL AND N.E. RADIUS
2) PROVIDE CITY APPROVED RFI REGARDING CHANGE FROM 16" TO 30" VERTS AND ONLY 17" LAP
3) POUR AT OWN RISK
03/02/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) BALANCE OF CMU WALL FOOTING AT EAST END, NORTH AND SOUTH FROM CORNERS
2) SECOND LIFT TO 8' TOP OUT AT WEST HALF OF NORTH CMY WALL FROM NORTH WEST CORNER
3) FIRST LIFT TO 4' AT TOP F APPROX 100 L.F. OK
02/25/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) SECOND LIFT TO 8 FT A TOP F AT CMU SITE WALL AT WEST END OK
02/24/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/23/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) WEST SITE WALL 1ST LIFT TO 4' AFFE AND 0' TO 100' OF NORTH SITE WALL, 1ST LIFT FROM N/W CORNER TO 4' AFFE OK
2) TERRACON SPECIAL INSPECTION
02/14/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) CONTINOUS FOOTING FOR NEW 8' CMU SITE WALL OK, ALL EXCEPT EAST END
2) SPECIAL INSPECTED BY TERRACON