Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/16/2012 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 10/17/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) EPOXY COATED TENSION PLATES AT 16 COLUMNS |
|
| 09/30/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 8 COLUMN TIE RODS (6 DBL & 2 SINGLES) AND TRENCHES |
|
| 09/07/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 8 WEST SIDE ARENA CONCRETE COLUMN BASES OK |
|
| 08/29/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 8 EAST SIDE ARENA CONCRETE COLUMN BASES NOTE: HAVE ELECTRICAL INSPECTION OF GROUND WIRES AT COLUMN BASES BEFORE POUR |
|
| 08/15/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) EAST SIDE COLUMN FOOTINGS-8 TOTAL |
|
| 08/05/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) WEST SIDE BLDG COLUMN FOOTINGS 8 TOTAL 6# F-2 & 2-#F-1'S WITH VERTS-OK TO POUR FOOTINGS ONLY |