Inspection Status: Cancelled
Inspection History: PLUMBING - PRE SLAB
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/16/2010 | PLUMBING - PRE SLAB | Cancelled | IVRS - RI canceled | |
| 09/16/2010 | PLUMBING - PRE SLAB | Approved | IVRS - Inspection :* | |
| 09/13/2010 | PLUMBING - PRE SLAB | Not ready for Inspection | IVRS - Inspection :* 1) DEMO'D PIPING TO BE CAPPED OFF IN THE WALL AND INSPECTED 2) NOT INSTALLED PER PLAN: SEE PLUMBING NOTES #7, 16 AND 25 3) SEE P.1 FIXTURE SCHEDULE-LAVATORY TO BE SUPPORTED BY A CARRIER 4) ALL WORK TO BE INSTALLED PER APPROVED PLAN 5) OK TO COVER UNDER FLOOR 6) NEW WATER HEATER, NOT SHOWN ON PLAN TO HAVE EXPANSION TANK AND VACUUM RELIEF VALVE |