Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T10CM02192

Parcel: 13303244B

Inspection Status: Approved

Inspection History: ELECTRIC - FINAL

Date Description Inspector Results Comments
12/23/2010 ELECTRIC - FINAL Approved IVRS - Inspection :*
12/14/2010 ELECTRIC - FINAL Denied IVRS - Inspection :
See detailed listing on site.| 999*
1) MIN BURRIAL DEPTH FOR PVC TO BE 18" NEC 300.5
2) EQUIPMENT GROUND TO CONNECT TO PV PANELS TO BE INSTALLED IN SAME RACEWAY AND CABLE
3) PLAN ONLY CALL FOR 16 PANELS 24 INSTALLED
4) INSTALL EQUIPMENT GROUND PER PLANS
5) INSTALL LABELING PER NEC 690
6) INSTALL LABEL AT SERVICE PANEL PER NOTE #11 LAST INSPECTION
7) INSTALL NEUTRAL CONDUCTOR PER PLANS
8) REVISE PLANS TO REFLECT INSTALLATION AS IT IS
11/30/2010 ELECTRIC - FINAL Denied IVRS - Inspection :
See detailed listing on site.| 999*
1) EXPOSE ALL NEW UNDERGROUND RACEWAYS. NEED TO MEET MINIMUM BURIAL REQUIREMENTS OF NEC 300.5
2) PVC ABOVE GRADE TO BE SCHEDULE 80
3) BOXES TO BE SECURED
4) NEED GROUNDING ELECTRODE SYSTEM CONNECTING TO INVERTER
5) LUGS LISTED FOR 1 WIRE TERMINATION
6) ALL CONDUCTOR OF BRANCH CIRCUIT TO BE INSTALLED TOGETHER IN SAME RACEWAY
7) CANNOT USE PANEL BOARD AS PASS THRU FOR BRANCH CIRCUIT TO PV SYSTEM
8) ARE MOTORS TO BE WIRED ?
9) WIRING TO PANELS NOT COMPLETE
10) NEED WORKING LABELS PER NEC 690
11) NEED LABEL AT PANEL PROVIDING LOCATION OF GENERATING SOURCES ON PROPERTY
12) CLOSE LB COVERS
13) STOPPED INSPECTION, TO MANY ITEMS TO LIST. INSTALL PER PLANS AND NEC. OBTAIN SERVICES OF QUALIFIED ELECTRICAL CONTRACTOR