Inspection Status: Approved
Inspection History: ELECTRIC - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/01/2011 | ELECTRIC - PROGRESS | Approved | ||
| 07/14/2011 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :*TRANSFORMER & PANELS ON EAST STAIRWAYS OK | |
| 04/14/2011 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 04/13/2011 | ELECTRIC - PROGRESS | Denied | IVRS - Inspection : The wiring is not complete or does not comply with code.| 245* |
|
| 03/31/2011 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* 1) SECOND FLOOR PVC RUNS IN FLOOR OK WEST SIDE PARKING STRUCTURE 2) ELECTRIC RUN TO SUB PANEL WITH MAIN DISCONNECT FOR SERVICE TEMP OK |
|
| 03/04/2011 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* 1) SEAL OFF, LISTED LAMP OR NOT 2' CELL ASK 2 |
|
| 02/25/2011 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* 1) EAST SIDE 2ND FLOOR PARKING LEVEL OK |
|
| 02/22/2011 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* 1) EAST, WEST AND CENTER BAY POWER FOR SERVICE BRANCHES 2) 3 LIGHT BOXES ON NORTH WALL ON SERVICE RAMP |
|
| 02/10/2011 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* 1) WEST SERVICE BY WALL OUTLETS OK 2) 3/0 UFER FOR SES IN FOOTER OK |
|
| 02/02/2011 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* 1) MIDDLE OF SERVICE BLDG STUBS FOR POWER AND CALL BACK WHEN BOXES ARE INSTALLED IN WALL |