Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - HYDRONIC PIPING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/09/2011 | MECHANICAL - HYDRONIC PIPING | Approved | IVRS - Inspection :* | |
| 11/02/2011 | MECHANICAL - HYDRONIC PIPING | Partial Approval | IVRS - Inspection :* 1) HYDRO TEST OF MECHANICAL ROOM PIPING OK, OK TO INSULATE 2) DUCT WORK AND HYDRO PIPING ABOVE T-BAR CEILINGS OK TO COVER |
|
| 10/27/2011 | MECHANICAL - HYDRONIC PIPING | Not ready for Inspection | IVRS - Inspection :* | |
| 10/14/2011 | MECHANICAL - HYDRONIC PIPING | Partial Approval | IVRS - Inspection :* 1) HYDRO PIPING TO TV UNITS PRESSURE TEST OK, OK TO COMPLETE INSULATION |
|
| 10/13/2011 | MECHANICAL - HYDRONIC PIPING | Not ready for Inspection | IVRS - Inspection :* | |
| 09/22/2011 | MECHANICAL - HYDRONIC PIPING | Partial Approval | IVRS - Inspection :* 1) HYDRO RISER TO BLDG 1 HAS MANUAL BLEED VALVES ABOVE HARD LID WITH NO ACCESS, PROVIDE ACCESS 2) NO OTHER COMPLETED WORK OBSERVED |
|
| 08/31/2011 | MECHANICAL - HYDRONIC PIPING | Not ready for Inspection | IVRS - Inspection :* | |
| 07/19/2011 | MECHANICAL - HYDRONIC PIPING | Not ready for Inspection | IVRS - Inspection :* |