Permit: T10CM01890

Parcel: 11942006E

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
12/02/2011 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
11/23/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) OK TO CLOSE UP MONUMENT SIGNAGE AND POUR
10/27/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) NEW BRIDGE SLAB OK
10/26/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
09/30/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 4 CULVERT SUPPORTS OK WITH SPECIAL INSPECTION
09/29/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) CALL BACK FOR BRIDGE WHEN SUPPORTS BUTT END UP
2) SEAT WALL FOOTING FOR LAST RAMADA
09/28/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) REFER TO PREVIOUS NOTES
09/27/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) EAST ABATEMENT WILL NEED EPOXY REBAR FOR WING WALLS
2) EAST SIDE EXCEPT HARD LIDS AND CORRIDOR EXCEPT HARD LIDS
09/23/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CULVERT SLAB ON GRADE AND W ABUTMENT WALL
09/09/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) REBAR FOR 8 BRIDGE CAISSIONS OK
2) NEEDS SPECIAL INSPECTION, HAS TO BE ON SITE WHEN SETTING CAISSIONS AND POURING THEM
09/07/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) MONUMENT WALLS LEFT
07/21/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 1) SEAT WALL FOOTING EAST OF BLDG
07/01/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) FOOTING FOR 58' OF RETAINING WALL WEST OF NORTH BB COURT
2) BENCH SEAT SOUTHWEST CORNER BLDG 5
06/28/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 45' OF RETAINING WALL BETWEEN BLDG 4 & 5
06/22/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 4 BENCH SEATS BETWEEN 5 & 6
2) 2 BENCH SEATS AND ALCOVE NW END OF BLDG 4
06/03/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) SEAT WALL WEST OF BLDG 7
05/17/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) SITE WALL FOOTING WEST OF BLDG 7
05/16/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 4 RAMADA SEATS FOOTINGS AS CHECKED ON MAIN PLAN
05/10/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) SITE WALL FOOTING APPROX 45' EAST SIDE OF BLDG #3 OK TO POUR FOOTING
05/06/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) SITE WALL FOOTING EAST SIDE OF BLDG #3
04/29/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
02/17/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/10/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
01/31/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 8-F7 FOOTINGS AND 3 F5 FOOTING
01/19/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
12/09/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) REMAINING PERIMETER FOOTING AS MARKED ON 1/2 SET TO BE SPECIAL INSPECTED
11/19/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) AS MARKED ON 1/2 SET SPECIAL INSPECTED
11/18/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*AS MARKED ON 1/2 SET SPECIAL INSPECTED
11/17/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) AS MARKED ON 1/2 SET SPECIAL INSPECTED