Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - ABOVE CEILING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/08/2011 | MECHANICAL - ABOVE CEILING | Approved | IVRS - Inspection :* | |
| 09/06/2011 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* | |
| 09/01/2011 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* FLEX DUCT IN LOCKER ROO, CORRIDOR TO BE STRAPPED UP OFF OF LIGHT FIXTURE SEAL DUCT JOINTS WHERE RE-HEAT COIL CONNECT COMPLETE DUCT INSULATION PROVIDE CLIPS ON RETURN DUCT CONDENSATE NOT COMPLETE AT IT ROOM THIS INSPECTION DOES NOT INCLUDE STAGE AREA OR KITCHEN OKAY FOR TILES ALL OTHER AREAS |
|
| 08/31/2011 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* | |
| 08/30/2011 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) PROGRESS AREAS |
|
| 08/25/2011 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* | |
| 08/24/2011 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* FRONT AREA ABOVE CIELING ONLY |
|
| 08/09/2011 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) SPOKE WITH JIM MILITELLO PER HIM OK TO LEAVE GAS CARD |
|
| 07/20/2011 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* | |
| 07/18/2011 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* | |
| 07/15/2011 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) DUCT ABOVE HARD LIDS OK TO COVER |
|
| 06/14/2011 | MECHANICAL - ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) PROVIDE TURNING VANES AT 90 DEGREE ELLS 2) OK TO INSULATE RAND PIPE |