Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/12/2011 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* | |
| 04/11/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 04/08/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 04/07/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 1ST LIFT ABOVE STEEL NORTH END |
|
| 04/06/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 04/05/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* TOP OUT AS MARKED ON PLAN | |
| 04/04/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 04/01/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) AS MARKED ON 1/2 SET |
|
| 03/31/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 03/30/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) EAST WALL ROOMS #312 AND 347 TO 20' 8" |
|
| 03/29/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) TOP OUT AS MARKED ON 1/2 SHEET |
|
| 03/28/2011 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* 1) NOT READY PER CONTRACTOR |
|
| 03/25/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) AS MARKED ON 1/2 SET SPECIAL INSPECTED |
|
| 03/24/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) WEST WALL ROOM #329,343 & 344, NORTH WALL ROOM #311 & 312, WEST WALL #341 & 342 4TH LIFT |
|
| 03/23/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* PARTIAL- AS MARKED ON PLAN. |
|
| 03/22/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) AS MARKED ON 1/2 SET |
|
| 03/21/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) AS MARKED ON PLAN |
|
| 03/17/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) AS MARKED ON 1/2 SET 2) SPECIAL INSPECTED |
|
| 03/16/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) AS MARKED ON PLAN-SPECIAL INSPECTED |
|
| 03/15/2011 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* 1) PER CONTRACTOR |
|
| 03/14/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) SOUTH AND EAST WALL ROOMS #300 AND 302 TO 16' 8" 2) SPECIAL INSPECTED |
|
| 03/11/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) AS MARKED ON 1/2 SET |
|
| 03/10/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) AS MARKED ON 1/2 SET SPECIAL INSPECTED |
|
| 03/04/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) AS MARKED ON 1/2 SET SPECIAL INSPECTED |
|
| 03/03/2011 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* 1) NOT READY PER CONTRACTOR |
|
| 03/01/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 1ST LIFT AND 2ND LIFT GABLE TOP OUT AS MARKED ON PLAN-SPECIAL INSPECTED |
|
| 02/28/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) AS MARKED ON PLAN, SPECIAL INSPECTED |
|
| 02/25/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) CMU WALLS AT 12'-16' 8"; #300 SOUTH WALL, 303 SOUTH WALL; 305 AND 307 WEST WALLS: CMU WALLS AT 16'-20' 8"-#311 WEST OK TO GROUT PROGRESS AREAS |
|
| 02/24/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) CMU WALLS AT 4'-8" A.F.F.E.: NORTH WALLS OF #317,314,335,336,336A,337 AND 339, EAST WALL #336 AT 4'-8" OK TO GROUT |
|
| 02/23/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) CMU WALLS: WEST WALLS #329, 333, 343, 344, FIRST LIFT AT 0'-4' 8", SOUTH WALL AT #325,326,342 AT 0'-4' 8", EAST WALLS #325 TO 332 0-4' 8", SOUTH WALL #338, GROUT ABOVE DBL DOORS (INCULDED) |
|
| 02/22/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) CMU WALLS AT 18'-8" GL: 7/D-E; C-D/3-7; WALLS AT 16'-8": GL: C/1-3; AT 12'-8" GL: 1/C-M |
|
| 02/17/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 02/16/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 02/15/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) CMU WALLS AT 12'-8"; GL: C.5-D/1.5-6.5 6.5/D-A; A/7-9, 8/A-B, B/8-8.5 CMU WALLS AT 4'-8"-GL: 2.5/L-O; 0-N.5/3.7.5 OK TO GROUT PROGRESS AREAS |
|
| 02/11/2011 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* 1) CONTRACTOR CANCELLED |
|
| 02/08/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* PARTIAL AS MARKED ON 1/2 SET |
|
| 02/01/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1ST LIFT AS MARKED ON PLAN |
|
| 01/19/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) AS MARKED ON 1/2 SET SPECIAL INSPECTED |
|
| 11/15/2010 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* |