Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T10CM01853
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/11/2013 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
09/25/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SCUPPER BASE AT ESCALANTE PARK ENTRY OK TO POUR PROGRESS AREAS | |
09/13/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SCUPPER BASEAT ESCALAMTE OK TO POUR | |
09/12/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CONTRACTOR POURING CONCRETE FOR TWO NEW SCUPPERS ALONG DRAINAGE WAY AT NORTH SIDE OF NEW PATHWAY. RE-BAR HAS BEEN INSTALLED PER APPROVED PLAN. | |
08/16/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 5 LIGHT POLE CAISSON FOOTINGS- OK TO POUR PROGRESS AREAS. | |
08/14/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 7 LIGHT POLE CAISSON FOOTINGS- AT ENTRY AND WALKING PATH | |
08/09/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 6 LIGHT POLES BASES- SW CORNER SOUTH AND WEST SIDE OF DRIVING RANGE. OK TO POUR PROGRESS AREAS |
|
08/03/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 2 LIGHT POLE BASES- SOUTH OF DRIVING RANGE | |
08/02/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | LIGHT POLE BASE AT DRIVING RANGE OK TO POUR | |
07/10/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* |