08/23/2011 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* | |
08/22/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 2ND LIFT ON PUMP ROOM AFTER HRS. INSP. CK #9591 - $165.00 FEE |
|
08/19/2011 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* | |
08/17/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 1ST LIFT PUMP ROOM |
|
06/21/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) TOP OUT EQUIPMENT ROOM |
|
06/09/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 44' 6" ON STAIRWAY #1 AND 1ST LIFT ON EQUIPMENT ROOM |
|
06/03/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | STAIR 1 OK TO 37'6" | |
05/31/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | STAIR ONE TO 32'6" | |
05/17/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) TOP OUT STAIRWAY AND ELEVATOR #2 |
|
05/16/2011 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* | |
05/11/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 55' 4" LIFT ON STAIRWAY #2 |
|
05/09/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 46' LIFT ON STAIRWAYS #? |
|
05/03/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 44'6" ON STAIRWAY #2 26'6" ON STAIRWWLL #1 | |
04/20/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
04/20/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | B/10-11 2ND LIFT | |
04/19/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
04/14/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
04/13/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 43' LIFT ON STAIRWAY #2 |
|
04/12/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) ELEVATION SHAFT TO 43' OK WITH COMPLIANT SPECIAL INSPECTION |
|
04/05/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 36' LIFT AT STAIRWELL #1, 17'4" LIFT STAIRWELL #2 | |
03/24/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) ELEVATOR AND STAIRWELL #1 34' LIFT |
|
03/23/2011 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* NOT READY- PARTIAL- GROUND LEVEL EAST |
|
03/02/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) PROGRESS LIFT 32' ON ELEVATOR SHAFT |
|
02/28/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) LEVEL 3 OK |
|
02/01/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 7TH LIFT ON STAIRWAY AND ELEVATOR #1 |
|
01/31/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) STAIRWAY #1 12' LIFT |
|
01/27/2011 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* | |
01/21/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) STAIRWAY AND ELEVATOR SHAFT 3RD LIFT |
|
01/19/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 2ND LIFT GL F.8/107-12, F.5-F.8/10.7 |
|
01/13/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 1ST LIFT GL F.5-F.2/10.6; F.2/10.6-11.6 |
|
12/17/2010 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 20' LIFT AT ELEVATOR SHAFT |
|
12/15/2010 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) HORIZONTAL: GL 3/E-D, 2.5/C-D, C/2.5-3, C-A/3 |
|
12/14/2010 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 3RD LIFT ELEVATOR |
|
12/08/2010 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 2ND LIFT ELEVATOR SHAFT, GL 7-8/E-F 1ST LIFT |
|
12/07/2010 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* | |
12/06/2010 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* | |
12/05/2010 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) GL 3-7/E 1ST LIFT |
|
11/30/2010 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 1ST LIFT ELEVATOR SHAFT |