Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T10CM01795

Parcel: 11717023D


Addresses:

88 E BROADWAY BL


Inspection Status: Approved

Inspection History: BUILDING PRE-SLAB

Permit Number - T10CM01795

Inspection Description - BUILDING PRE-SLAB

Inspection Status - Approved

Date Description Inspector Results Comments
03/03/2011 BUILDING PRE-SLAB Approved
02/25/2011 BUILDING PRE-SLAB Partial Approval LEVEL 4 EAST UNDER CONST.
02/23/2011 BUILDING PRE-SLAB Partial Approval
02/21/2011 BUILDING PRE-SLAB Partial Approval LEVEL 4 SW OK TO PLACE (PM INSPECTION)
02/08/2011 BUILDING PRE-SLAB Partial Approval LEVEL 3 S-E OK TO PLACE
02/07/2011 BUILDING PRE-SLAB Partial Approval LEVEL 3 SE :
1) TENDONS OVER OUTLET J/11.5
2) RENTRY BARS AT OPENING 12-13/I-J
3) EXTRA REINFORCING AT PENETRATIONS I/13
4) CONCRETE COVER OF UNIFORM TENDONS @ CONDUITS ALL SLABS
5) PROFILE OF BANDEDS 11-12/F
02/04/2011 BUILDING PRE-SLAB Partial Approval
02/02/2011 BUILDING PRE-SLAB Partial Approval
02/01/2011 BUILDING PRE-SLAB Partial Approval AFTER HOUR INSPECTION 5:30 TO 7:30 PM. ROOF EAST SIDE OK TO PLACE
01/25/2011 BUILDING PRE-SLAB Partial Approval
01/24/2011 BUILDING PRE-SLAB Partial Approval LEVEL 9 WEST AND RAMP 2-3 (PM INSPECTION)
01/21/2011 BUILDING PRE-SLAB Partial Approval LEVEL 2 SE OK TO PLACE (PM INSPECTION)
01/19/2011 BUILDING PRE-SLAB Partial Approval COMPACTION FOR SOG AREA 1-3 OK. STILL NEED STEEL BEFORE PLACING SLAB
01/17/2011 BUILDING PRE-SLAB Partial Approval LEVEL 9 EAST OK TO PLACE (PM INSPECTION)
01/16/2011 BUILDING PRE-SLAB Partial Approval LEVEL 2 SW OK TO PLACE. (WEEKEND INSPECTION)
01/14/2011 BUILDING PRE-SLAB Partial Approval LEVEL 2 SW NOT READY
01/13/2011 BUILDING PRE-SLAB Partial Approval LEVEL 8 WEST SIDE OK TO PLACE. (PM INSPECTION)
01/12/2011 BUILDING PRE-SLAB Partial Approval
01/07/2011 BUILDING PRE-SLAB Partial Approval RAMP LEVEL 1 - 2 OK TO PLACE WHEN SPECIAL INSPECTOR CONFIRMS FINAL ADJUSTMENTS.
01/06/2011 BUILDING PRE-SLAB Partial Approval EAST LEVEL 8 OK TO PLACE (PM INSPECTION)
01/05/2011 BUILDING PRE-SLAB Partial Approval RESHORES & FORMS OK TO LEVEL 8 NORTH
01/04/2011 BUILDING PRE-SLAB Partial Approval LEVEL 7 WEST OK TO PLACE (PM INSPECTION 10 -12)
01/03/2011 BUILDING PRE-SLAB Partial Approval SOUTH PLAZA WEST SIDE PLACED OK. CORRECTIONS REQUIRED FOR EAST SIDE BEING MADE AT THIS TIME.
12/30/2010 BUILDING PRE-SLAB Partial Approval CORRECTIONS REQUIRED ON SOME ELECTRICAL INSTALLATIONS BEFORE POURING PLAZA LEVEL SOUTH.
12/29/2010 BUILDING PRE-SLAB Partial Approval PLAZA LEVEL SW REQUIRES FORMS TO BE ADJUSTED AT 8" TO 6" TRANSITION; RELOCATE ELECTRICAL IN BEAM LINE 15 OR INSTALL USING HEAVY STEEL BOXES; ADJUST #8 BARS IN BEAMS FOR CONCRETE COVERAGE.

PLAZA SE NOT READY
12/27/2010 BUILDING PRE-SLAB Partial Approval CLOSURE POURS LEVELS B2 & B3 READY ON NORTH SIDES
12/27/2010 BUILDING PRE-SLAB Partial Approval LEVEL 7 -E OK TO PLACE (PM INSPECTION)
12/22/2010 BUILDING PRE-SLAB Partial Approval BEAM PLAZA LEVEL LINE 15 OK TO PLACE
12/22/2010 BUILDING PRE-SLAB Partial Approval LEVEL 6 NW OK TO PLACE (PM INSPECTION 9-11)
12/20/2010 BUILDING PRE-SLAB Partial Approval CENTRAL PORTION OF SOUTH PLAZA LEVEL OK TO PLACE (PM INSPECTION)
12/19/2010 BUILDING PRE-SLAB Partial Approval MET ON SITE TO DISCUSS ASI 9 AND PLAZA POUR SCHEDULE
12/17/2010 BUILDING PRE-SLAB Partial Approval
12/16/2010 BUILDING PRE-SLAB Partial Approval
12/15/2010 BUILDING PRE-SLAB Partial Approval
12/09/2010 BUILDING PRE-SLAB Partial Approval CLOSURE POURS LEVEL B2 OK TO PLACE
12/06/2010 BUILDING PRE-SLAB Partial Approval LEVEL 5 NE OK TO PLACE
12/02/2010 BUILDING PRE-SLAB Partial Approval PM INSPECTION. 4TH LEVEL NW OK TO PLACE
11/29/2010 BUILDING PRE-SLAB Partial Approval STILL NEED TO PROPERLY SET DUCT BANK STEEL AT PLAZA LEVEL. ALSO MORE CONDUITS THAN ON ORIGINAL PLAN SO WE NEED RFI FOR ADDED WEIGHT FROM ENGINEER.
11/23/2010 BUILDING PRE-SLAB Partial Approval NE LEVEL 4 OK TO PLACE
11/22/2010 BUILDING PRE-SLAB Partial Approval PROGRESS ON LEVEL4 NE OK. RE-SHORING IS STILL NOT IN PLACE
11/19/2010 BUILDING PRE-SLAB Partial Approval BOTTOM OF DUCT BANK PLAZA LEVEL OK
11/18/2010 BUILDING PRE-SLAB Partial Approval NO NEW SLAB WORK READY. RE-SHORING FROM LEVEL 2-3 IS NOT IN PLACE. DO NOT START LEVEL 4 STEEL UNTIL REPLACED.
11/17/2010 BUILDING PRE-SLAB Partial Approval NW LEVEL 3 OK TO PLACE CONCRETE
11/11/2010 BUILDING PRE-SLAB Partial Approval NE LEVEL 3 OK TO PLACE
11/10/2010 BUILDING PRE-SLAB Partial Approval RAMP FROM B1 TO PLAZA LEVEL OK
11/05/2010 BUILDING PRE-SLAB Partial Approval OK TO PLACE NW LEVEL 2. CONDUIT RUNS ALTERED TO COME UP INTO RAISED FLOOR
11/04/2010 BUILDING PRE-SLAB Partial Approval SE LEVEL B1 OK TO PLACE
AFTER HOUR INSPECTION CHARGED FOR BLD AND ELEC
10/29/2010 BUILDING PRE-SLAB Partial Approval NE LEVEL 2 OK TO PLACE
10/28/2010 BUILDING PRE-SLAB Partial Approval SOUTH LEVEL B1 A-E OK TO PLACE WHEN SPECIAL INSPECTOR DOES FINAL APPROVAL
10/26/2010 BUILDING PRE-SLAB Partial Approval B2 - B1 SOUTH RAMP OK TO PLACE
10/19/2010 BUILDING PRE-SLAB Partial Approval NW PLAZA LEVEL OK TO PLACE WHEN SP. INSP CONFIRMS CORRECTION OF ITEMS FOUND AT TODAY'S WALKTHROUGH.
10/18/2010 BUILDING PRE-SLAB Partial Approval OK TO PLACE SE QUADRANT OF LEVEL B2
10/14/2010 BUILDING PRE-SLAB Partial Approval LEVEL B2 A-E/11-16 ALMOST READY. NEED QC ON REBAR CHAIRS AND CONDUIT RUNS. ALSO NEED STUDS AT LINE 14 COLUMNS.
10/13/2010 BUILDING PRE-SLAB Partial Approval PROGRESS ONLY. NOTHING READY TO PLACE. HAVE ISSUE WITH TENDON REPAIR LEVEL B2. NEED ENGINEER APPROVED FIX.
10/12/2010 BUILDING PRE-SLAB Partial Approval PROGRESS ONLY. NOTHING READY TO PLACE. POUR SCHEDULE ALTERED FOR TOMORROW NIGHT, THEN FRIDAY, THEN TUESDAY IF NO FURTHER ISSUES ARISE.
10/05/2010 BUILDING PRE-SLAB Partial Approval MEETING TO DISCUSS Q. C. ISSUES WITH ENGINEER AND SUNTEC
10/02/2010 BUILDING PRE-SLAB Partial Approval OK TO PLACE LEVEL B1 A-E/3-11
10/01/2010 BUILDING PRE-SLAB Partial Approval PROGRESS LEVEL B1 @ A-E/3-11 OK. MILD STEEL OK. CGS AT BEAM LOW POINTS MUST BE CORRECTED AT ALL BEAMS (1" TOO HIGH). CGS AT COLS MUST ALSO BE CORRECTED.

STRESSING OF LEVEL B1 @ E-J/3-11 IS POORLY DONE. ENGINEER TO PHYSICALLY REVIEW WHAT CONTRACTOR HAS DONE AND MAKE RECOMMENDATION, PROBABLE LIFT-OFF AND RESTRESSING WILL BE REQUIRED AS WEDGES ARE NOT PROPERLY SEATED. APPEARS THAT HEADS WERE NOT PROPERLY CLEANED AND 4 TENDONS HAVE ALREADY SUFFERED SEVERE DAMAGE.
09/28/2010 BUILDING PRE-SLAB Partial Approval PLACEMENT OF CONCRETE LEVEL B1 3-11/E-J COMPLETED OK. EARLY BREAKS INDICATE STRESSING MAY BE DONE TOMORROW.

SHORING FOR ADJACENT AREA INCOMPLETE

SELECT FILL AT RAMP LEVEL B3 NEAR COMPLETION. AB LAYER STILL TO BE PLACED.
09/27/2010 BUILDING PRE-SLAB Partial Approval LEVEL B1 AREA 3-11/E-J OK TO PLACE
09/22/2010 BUILDING PRE-SLAB Partial Approval LEVEL B2 AREA A-E/3-11 OK TO PLACE
09/21/2010 BUILDING PRE-SLAB Partial Approval LEVEL B2 AREA A-E / 3-11 STILL REQUIRES ADDED STEEL AND FINAL ELECTRIC RUNS INSTALLED. PROGRESS GENERALLY OK.
09/20/2010 BUILDING PRE-SLAB Partial Approval STILL NEED MILD STEEL, UNIFORM AND TEMP TENDONS LEVEL B2 AREA A-E/4-11.

FRIDAY POUR OF B-2 AREA E-J/3-11 COMPLETED OK. BREAKS FOR CONCRETE OVER 4KPSI SO TENSIONING IS BEING DONE TODAY. NEED RFI FOR FUTURE FIX OF 3 TEMP TENDONS BETWEEN E AND F TERMINATING AT COLD JOINT OF SLAB.
09/17/2010 BUILDING PRE-SLAB Partial Approval LEVEL B2 AREA 3-11/E-J CABLES AND MILD STEEL OK. SEVERAL PROBLEMS WITH THE ELECTRICAL CONDUITS IN THIS AREA. MET WITH E.O.R. TO DISCUSS NECESSARY REPAIRS. OK TO PLACE CONCRETE WHEN SPECIAL INSPECTOR CONFIRMS CORRECTIONS TO ELECTRICAL.
09/16/2010 BUILDING PRE-SLAB Partial Approval PROGRESS LEVEL B-2 AREA E-J / 3-11