Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
Permit Number - T10CM01795
Inspection Description - BUILDING PRE-SLAB
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/03/2011 | BUILDING PRE-SLAB | Approved | ||
02/25/2011 | BUILDING PRE-SLAB | Partial Approval | LEVEL 4 EAST UNDER CONST. | |
02/23/2011 | BUILDING PRE-SLAB | Partial Approval | ||
02/21/2011 | BUILDING PRE-SLAB | Partial Approval | LEVEL 4 SW OK TO PLACE (PM INSPECTION) | |
02/08/2011 | BUILDING PRE-SLAB | Partial Approval | LEVEL 3 S-E OK TO PLACE | |
02/07/2011 | BUILDING PRE-SLAB | Partial Approval | LEVEL 3 SE : 1) TENDONS OVER OUTLET J/11.5 2) RENTRY BARS AT OPENING 12-13/I-J 3) EXTRA REINFORCING AT PENETRATIONS I/13 4) CONCRETE COVER OF UNIFORM TENDONS @ CONDUITS ALL SLABS 5) PROFILE OF BANDEDS 11-12/F |
|
02/04/2011 | BUILDING PRE-SLAB | Partial Approval | ||
02/02/2011 | BUILDING PRE-SLAB | Partial Approval | ||
02/01/2011 | BUILDING PRE-SLAB | Partial Approval | AFTER HOUR INSPECTION 5:30 TO 7:30 PM. ROOF EAST SIDE OK TO PLACE | |
01/25/2011 | BUILDING PRE-SLAB | Partial Approval | ||
01/24/2011 | BUILDING PRE-SLAB | Partial Approval | LEVEL 9 WEST AND RAMP 2-3 (PM INSPECTION) | |
01/21/2011 | BUILDING PRE-SLAB | Partial Approval | LEVEL 2 SE OK TO PLACE (PM INSPECTION) | |
01/19/2011 | BUILDING PRE-SLAB | Partial Approval | COMPACTION FOR SOG AREA 1-3 OK. STILL NEED STEEL BEFORE PLACING SLAB | |
01/17/2011 | BUILDING PRE-SLAB | Partial Approval | LEVEL 9 EAST OK TO PLACE (PM INSPECTION) | |
01/16/2011 | BUILDING PRE-SLAB | Partial Approval | LEVEL 2 SW OK TO PLACE. (WEEKEND INSPECTION) | |
01/14/2011 | BUILDING PRE-SLAB | Partial Approval | LEVEL 2 SW NOT READY | |
01/13/2011 | BUILDING PRE-SLAB | Partial Approval | LEVEL 8 WEST SIDE OK TO PLACE. (PM INSPECTION) | |
01/12/2011 | BUILDING PRE-SLAB | Partial Approval | ||
01/07/2011 | BUILDING PRE-SLAB | Partial Approval | RAMP LEVEL 1 - 2 OK TO PLACE WHEN SPECIAL INSPECTOR CONFIRMS FINAL ADJUSTMENTS. | |
01/06/2011 | BUILDING PRE-SLAB | Partial Approval | EAST LEVEL 8 OK TO PLACE (PM INSPECTION) | |
01/05/2011 | BUILDING PRE-SLAB | Partial Approval | RESHORES & FORMS OK TO LEVEL 8 NORTH | |
01/04/2011 | BUILDING PRE-SLAB | Partial Approval | LEVEL 7 WEST OK TO PLACE (PM INSPECTION 10 -12) | |
01/03/2011 | BUILDING PRE-SLAB | Partial Approval | SOUTH PLAZA WEST SIDE PLACED OK. CORRECTIONS REQUIRED FOR EAST SIDE BEING MADE AT THIS TIME. | |
12/30/2010 | BUILDING PRE-SLAB | Partial Approval | CORRECTIONS REQUIRED ON SOME ELECTRICAL INSTALLATIONS BEFORE POURING PLAZA LEVEL SOUTH. | |
12/29/2010 | BUILDING PRE-SLAB | Partial Approval | PLAZA LEVEL SW REQUIRES FORMS TO BE ADJUSTED AT 8" TO 6" TRANSITION; RELOCATE ELECTRICAL IN BEAM LINE 15 OR INSTALL USING HEAVY STEEL BOXES; ADJUST #8 BARS IN BEAMS FOR CONCRETE COVERAGE. PLAZA SE NOT READY |
|
12/27/2010 | BUILDING PRE-SLAB | Partial Approval | CLOSURE POURS LEVELS B2 & B3 READY ON NORTH SIDES | |
12/27/2010 | BUILDING PRE-SLAB | Partial Approval | LEVEL 7 -E OK TO PLACE (PM INSPECTION) | |
12/22/2010 | BUILDING PRE-SLAB | Partial Approval | BEAM PLAZA LEVEL LINE 15 OK TO PLACE | |
12/22/2010 | BUILDING PRE-SLAB | Partial Approval | LEVEL 6 NW OK TO PLACE (PM INSPECTION 9-11) | |
12/20/2010 | BUILDING PRE-SLAB | Partial Approval | CENTRAL PORTION OF SOUTH PLAZA LEVEL OK TO PLACE (PM INSPECTION) | |
12/19/2010 | BUILDING PRE-SLAB | Partial Approval | MET ON SITE TO DISCUSS ASI 9 AND PLAZA POUR SCHEDULE | |
12/17/2010 | BUILDING PRE-SLAB | Partial Approval | ||
12/16/2010 | BUILDING PRE-SLAB | Partial Approval | ||
12/15/2010 | BUILDING PRE-SLAB | Partial Approval | ||
12/09/2010 | BUILDING PRE-SLAB | Partial Approval | CLOSURE POURS LEVEL B2 OK TO PLACE | |
12/06/2010 | BUILDING PRE-SLAB | Partial Approval | LEVEL 5 NE OK TO PLACE | |
12/02/2010 | BUILDING PRE-SLAB | Partial Approval | PM INSPECTION. 4TH LEVEL NW OK TO PLACE | |
11/29/2010 | BUILDING PRE-SLAB | Partial Approval | STILL NEED TO PROPERLY SET DUCT BANK STEEL AT PLAZA LEVEL. ALSO MORE CONDUITS THAN ON ORIGINAL PLAN SO WE NEED RFI FOR ADDED WEIGHT FROM ENGINEER. | |
11/23/2010 | BUILDING PRE-SLAB | Partial Approval | NE LEVEL 4 OK TO PLACE | |
11/22/2010 | BUILDING PRE-SLAB | Partial Approval | PROGRESS ON LEVEL4 NE OK. RE-SHORING IS STILL NOT IN PLACE | |
11/19/2010 | BUILDING PRE-SLAB | Partial Approval | BOTTOM OF DUCT BANK PLAZA LEVEL OK | |
11/18/2010 | BUILDING PRE-SLAB | Partial Approval | NO NEW SLAB WORK READY. RE-SHORING FROM LEVEL 2-3 IS NOT IN PLACE. DO NOT START LEVEL 4 STEEL UNTIL REPLACED. | |
11/17/2010 | BUILDING PRE-SLAB | Partial Approval | NW LEVEL 3 OK TO PLACE CONCRETE | |
11/11/2010 | BUILDING PRE-SLAB | Partial Approval | NE LEVEL 3 OK TO PLACE | |
11/10/2010 | BUILDING PRE-SLAB | Partial Approval | RAMP FROM B1 TO PLAZA LEVEL OK | |
11/05/2010 | BUILDING PRE-SLAB | Partial Approval | OK TO PLACE NW LEVEL 2. CONDUIT RUNS ALTERED TO COME UP INTO RAISED FLOOR | |
11/04/2010 | BUILDING PRE-SLAB | Partial Approval | SE LEVEL B1 OK TO PLACE AFTER HOUR INSPECTION CHARGED FOR BLD AND ELEC |
|
10/29/2010 | BUILDING PRE-SLAB | Partial Approval | NE LEVEL 2 OK TO PLACE | |
10/28/2010 | BUILDING PRE-SLAB | Partial Approval | SOUTH LEVEL B1 A-E OK TO PLACE WHEN SPECIAL INSPECTOR DOES FINAL APPROVAL | |
10/26/2010 | BUILDING PRE-SLAB | Partial Approval | B2 - B1 SOUTH RAMP OK TO PLACE | |
10/19/2010 | BUILDING PRE-SLAB | Partial Approval | NW PLAZA LEVEL OK TO PLACE WHEN SP. INSP CONFIRMS CORRECTION OF ITEMS FOUND AT TODAY'S WALKTHROUGH. | |
10/18/2010 | BUILDING PRE-SLAB | Partial Approval | OK TO PLACE SE QUADRANT OF LEVEL B2 | |
10/14/2010 | BUILDING PRE-SLAB | Partial Approval | LEVEL B2 A-E/11-16 ALMOST READY. NEED QC ON REBAR CHAIRS AND CONDUIT RUNS. ALSO NEED STUDS AT LINE 14 COLUMNS. | |
10/13/2010 | BUILDING PRE-SLAB | Partial Approval | PROGRESS ONLY. NOTHING READY TO PLACE. HAVE ISSUE WITH TENDON REPAIR LEVEL B2. NEED ENGINEER APPROVED FIX. | |
10/12/2010 | BUILDING PRE-SLAB | Partial Approval | PROGRESS ONLY. NOTHING READY TO PLACE. POUR SCHEDULE ALTERED FOR TOMORROW NIGHT, THEN FRIDAY, THEN TUESDAY IF NO FURTHER ISSUES ARISE. | |
10/05/2010 | BUILDING PRE-SLAB | Partial Approval | MEETING TO DISCUSS Q. C. ISSUES WITH ENGINEER AND SUNTEC | |
10/02/2010 | BUILDING PRE-SLAB | Partial Approval | OK TO PLACE LEVEL B1 A-E/3-11 | |
10/01/2010 | BUILDING PRE-SLAB | Partial Approval | PROGRESS LEVEL B1 @ A-E/3-11 OK. MILD STEEL OK. CGS AT BEAM LOW POINTS MUST BE CORRECTED AT ALL BEAMS (1" TOO HIGH). CGS AT COLS MUST ALSO BE CORRECTED. STRESSING OF LEVEL B1 @ E-J/3-11 IS POORLY DONE. ENGINEER TO PHYSICALLY REVIEW WHAT CONTRACTOR HAS DONE AND MAKE RECOMMENDATION, PROBABLE LIFT-OFF AND RESTRESSING WILL BE REQUIRED AS WEDGES ARE NOT PROPERLY SEATED. APPEARS THAT HEADS WERE NOT PROPERLY CLEANED AND 4 TENDONS HAVE ALREADY SUFFERED SEVERE DAMAGE. |
|
09/28/2010 | BUILDING PRE-SLAB | Partial Approval | PLACEMENT OF CONCRETE LEVEL B1 3-11/E-J COMPLETED OK. EARLY BREAKS INDICATE STRESSING MAY BE DONE TOMORROW. SHORING FOR ADJACENT AREA INCOMPLETE SELECT FILL AT RAMP LEVEL B3 NEAR COMPLETION. AB LAYER STILL TO BE PLACED. |
|
09/27/2010 | BUILDING PRE-SLAB | Partial Approval | LEVEL B1 AREA 3-11/E-J OK TO PLACE | |
09/22/2010 | BUILDING PRE-SLAB | Partial Approval | LEVEL B2 AREA A-E/3-11 OK TO PLACE | |
09/21/2010 | BUILDING PRE-SLAB | Partial Approval | LEVEL B2 AREA A-E / 3-11 STILL REQUIRES ADDED STEEL AND FINAL ELECTRIC RUNS INSTALLED. PROGRESS GENERALLY OK. | |
09/20/2010 | BUILDING PRE-SLAB | Partial Approval | STILL NEED MILD STEEL, UNIFORM AND TEMP TENDONS LEVEL B2 AREA A-E/4-11. FRIDAY POUR OF B-2 AREA E-J/3-11 COMPLETED OK. BREAKS FOR CONCRETE OVER 4KPSI SO TENSIONING IS BEING DONE TODAY. NEED RFI FOR FUTURE FIX OF 3 TEMP TENDONS BETWEEN E AND F TERMINATING AT COLD JOINT OF SLAB. |
|
09/17/2010 | BUILDING PRE-SLAB | Partial Approval | LEVEL B2 AREA 3-11/E-J CABLES AND MILD STEEL OK. SEVERAL PROBLEMS WITH THE ELECTRICAL CONDUITS IN THIS AREA. MET WITH E.O.R. TO DISCUSS NECESSARY REPAIRS. OK TO PLACE CONCRETE WHEN SPECIAL INSPECTOR CONFIRMS CORRECTIONS TO ELECTRICAL. | |
09/16/2010 | BUILDING PRE-SLAB | Partial Approval | PROGRESS LEVEL B-2 AREA E-J / 3-11 |