Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
Permit Number - T10CM01664
Inspection Description - REINFORCED MASONRY PRE-GROUT
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/02/2011 | REINFORCED MASONRY PRE-GROUT | Approved | ||
12/16/2010 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 1) TOP POUT ON SOUTH DRIVE THRU CMU COLUMN OK | |
12/15/2010 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* 1) CONTRACTOR CANCELLED |
|
12/13/2010 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) BEAM SADDLE-WOOD BEAM ON CMU WALL DETAIL #234, PAGE S5.2-AT 13'-6" OK TO GROUT 2) LEDGER SPLICE PER DETAIL #L2 ON LEDGER SCHEDULE; ROOMS #1, 2, 3, 4, 5, 6, 7 AND 13-OK TO COVER PENDING ELECTRIC AND PLUMBING INTERMEDIATES |
|
12/10/2010 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) DRIVE THRU ADDITION SOUTH CMU COLUMN 2ND LIFT TO 8 FT AFFE-OK TO GROUT |
|
12/09/2010 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 1ST LIFT OF CMU S/W COLUMN OF ADDITION 2) 5 EXTERIOR CMU COLUMN INFILLS-TOP OUT OK |
|
12/07/2010 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) CMU COLUMN EXTERIOR IN FILLS (5 TOTAL) TO 16 FEET (NEXT TO LAST LIFT) |
|
12/03/2010 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 6 BEAM BEARING SADDLES AT CMU WALLS DETAILS #201,216,218,217 AND 214 2) 3RD LIFT ON COLUMN INFILLS DETAIL #104, PAGE S4.1-OK TO GROUT PROGRESS AREAS |
|
11/23/2010 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 2 STRUCTURAL CMU COLUMNS AT NORTH SITE OF SERVICE DRIVE TOP OUT 2) SOUTH AND WEST CMU WALLS AT SERVICE ADVISERS OFFICE TOP OUT 3) 5-CMU COLUMNS AT NORTH AND WEST INFILLS-2ND LIFT |
|
11/19/2010 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) ADA RAMP WALLS PER DETAILS #102 & 103; SERVICE ENTRY AREA: NORTH WALL AND COLUMNS AT 8'-12'; SOUTH WALL AT 8'-12' AND 4'-8' (EAST PORTION) OK TO GROUT PROGRESS AREAS |
|
11/12/2010 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) NORTH SIDE OF SERVICE ADDITION AT 4'; SOUTH SIDE AT 4'-8'; SERVICE DRIVE NORTH COLUMNS AT 8'-12' OK TO GROUT |