Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/26/2011 | ENGINEERING - FINAL | Approved | ALL PREVIOUSLY ITEMS HAVE BEEN ADDRESSED EITHER BY COMPLETING THE ITEMS OR THROUGH THE REVISED DRAWINGS. | |
| 04/22/2011 | ENGINEERING - FINAL | Denied | 1) REMOVE ALL CONSTRUCTION EQUIP, MATERIAL, AND PORTA-JON. 2) COMPLETE ALL SITE WORK ASSOCIATED W/THE BLDG. TO INCLUDE THE STORM WATER DRAINAGE SWALE THAT CARRIES ROOF DRAINAGE OFF SITE. 3) COMPLETE AND/OR SEPARATE REMAINING BLDG CONSTRUCTION FROM PUBLIC ACCESS. |
|
| 04/22/2011 | ENGINEERING - FINAL | Partial Approval | ITEMS 1 AND 3 FROM THE PREVIOUS INSPECTION HAS BEEN COMPLETED BUT THE FOLLOWING ITEMS HAVE BEEN ADDED AND WILL NEED TO BE COMPLETED PRIOR TO ISSUEING THE FINAL C OF O FOR THIS SITE DUE TO HEALTH AND SAFETY ISSUES. 1) REMOVE THE OPEN DRIVEWAY AND SIDEWALK ADJACENT TO THIS SITE ON THE EAST SIDE OF COUNTRY CLUB AND REPLACE IT WITH VERTICAL CURB AND NEW SIDEWALK. THIS DRIVEWAY HAS NOT BEE SHOWN ON THE PLANS, IT IS DEPICTED AS BEING JUST SIDEWALK AND VERTICAL CURB. HAVE THE ENGINEER OF RECORD CONTACT STEVE SHIELDS AND JASON GREEN ABOUT THE CHANGES THAT NEED TO BE MADE. THIS MAY REQUIRE AN ADDITIONAL RIGHT-OF-WAY PERMIT FROM THE TRANSPORTATION DEPARTMENT. 2) COMPLETE THE SIDEWALK FROM COUNTRY CLUB AS SHOWN ON THE APPROVED PLANS. THIS WILL REQUIRE THAT IT IS DESIGNED TO ALLOW FOR ALL WEATHER ACCESS IN THE AREAS WHERE IT CROSSES OVER THE EXISTING DRAINAGE CHANNELS. 3) STABALIZE ALL AREAS THAT ARE SOIL THAT HAVE BEEN DISTURBED DURING CONSTRUCTION AS REQUIRED BY THE LAND USE CODE. THIS CAN EITHER BE DONE BY THE PLACEMENT OF DECOMPOSED GRANITE OR BY REVEGITATING THE AREA, CONTACT JOSEPH LINVILLE OR ANDREW CONNOR IF YOU HAVE ANY QUESTIONS. |