Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T10CM01509

Parcel: 11717023D


Addresses:

88 E BROADWAY BL


Inspection Status: Approved

Inspection History: BUILDING PRE-SLAB

Permit Number - T10CM01509

Inspection Description - BUILDING PRE-SLAB

Inspection Status - Approved

Date Description Inspector Results Comments
02/08/2011 BUILDING PRE-SLAB Approved SEE SHELL PERMIT FOR ALL REMAINING INSPECTION RESULTS
01/05/2011 BUILDING PRE-SLAB Partial Approval
12/30/2010 BUILDING PRE-SLAB Partial Approval SOUTH PLAZA LEVEL REQUIRES CORRECTIONS TO ELECTRICAL INSTALLATION PRIOR TO OUTSIDE POURS.
12/06/2010 BUILDING PRE-SLAB Partial Approval LEVEL 5 NE NEED TO CHIP DOWN COLS EXTENDING INTO BEAMS...NEED TO FINISH WORK
12/06/2010 BUILDING PRE-SLAB Partial Approval LEVEL 5 NE OK TO PLACE PM INSP
12/02/2010 BUILDING PRE-SLAB Partial Approval 4TH LEVEL NW IN PROGRESS. NEED TO FINISH ELECTRICAL & CLEAN UP STEEL.
12/02/2010 BUILDING PRE-SLAB Partial Approval PM INSPECTION. 4TH LEVEL NW OK TO PLACE
12/01/2010 BUILDING PRE-SLAB Partial Approval DUCT BANK OK TO PLACE
11/11/2010 BUILDING PRE-SLAB Partial Approval NE LEVEL 3 OK TO PLACE
11/10/2010 BUILDING PRE-SLAB Partial Approval RAMP FROM B1 TO PLAZA LEVEL OK
11/05/2010 BUILDING PRE-SLAB Partial Approval OK TO PLACE NW LEVEL 2. CONDUIT RUNS ALTERED TO COME UP INTO RAISED FLOOR
11/04/2010 BUILDING PRE-SLAB Partial Approval SE B1 OK TO PLACE
10/29/2010 BUILDING PRE-SLAB Partial Approval NE LEVEL 2 OK TO PLACE
10/28/2010 BUILDING PRE-SLAB Partial Approval LEVEL B1 SOUTH SIDE A- E OK TO PLACE WHEN SP INSP CONFIRMS FINAL CLEAN UP
10/26/2010 BUILDING PRE-SLAB Partial Approval SOUTH RAMP B2 - B1 OK TO PLACE
10/19/2010 BUILDING PRE-SLAB Partial Approval NW PLAZA LEVEL OK TO PLACE TONIGHT WHEN CORRECTIONS CONFIRMED BY SPECIAL INSPECTOR.
10/14/2010 BUILDING PRE-SLAB Partial Approval LEVEL B2 A-E/11-16 ALMOST READY. NEED QC ON REBAR CHAIRS AND CONDUIT RUNS. ALSO NEED STUDS AT LINE 14 COLUMNS.
10/13/2010 BUILDING PRE-SLAB Partial Approval PROGRESS ONLY. NOTHING READY TO PLACE
10/12/2010 BUILDING PRE-SLAB Partial Approval PROGRESS ONLY. NOTHING READY TO PLACE
10/02/2010 BUILDING PRE-SLAB Partial Approval OK TO PLACE LEVEL B1 A-E/3-11
10/01/2010 BUILDING PRE-SLAB Partial Approval PROGRESS LEVEL B1 @ A-E/3-11 OK. MILD STEEL OK. CGS AT BEAM LOW POINTS MUST BE CORRECTED AT ALL BEAMS (1" TOO HIGH). CGS AT COLS MUST ALSO BE CORRECTED.

STRESSING OF LEVEL B1 @ E-J/3-11 IS POORLY DONE. ENGINEER TO PHYSICALLY REVIEW WHAT CONTRACTOR HAS DONE AND MAKE RECOMMENDATION, PROBABLE LIFT-OFF AND RESTRESSING WILL BE REQUIRED AS WEDGES ARE NOT PROPERLY SEATED. APPEARS THAT HEADS WERE NOT PROPERLY CLEANED AND 4 TENDONS HAVE ALREADY SUFFERED SEVERE DAMAGE.
09/27/2010 BUILDING PRE-SLAB Partial Approval AREA 3-11/ E-J LEVEL B1 OK TO PLACE
09/22/2010 BUILDING PRE-SLAB Partial Approval LEVEL B2 AREA A-E/3-11 OK TO PLACE
09/21/2010 BUILDING PRE-SLAB Partial Approval LEVEL B2 AREA A-E / 3-11 STILL REQUIRES ADDED STEEL AND FINAL ELECTRIC RUNS INSTALLED. PROGRESS GENERALLY OK.
09/20/2010 BUILDING PRE-SLAB Partial Approval STILL NEED MILD STEEL, UNIFORM AND TEMP TENDONS LEVEL B2 AREA A-E/4-11.

FRIDAY POUR OF B-2 AREA E-J/3-11 COMPLETED OK. BREAKS FOR CONCRETE OVER 4KPSI SO TENSIONING IS BEING DONE TODAY. NEED RFI FOR FUTURE FIX OF 3 TEMP TENDONS BETWEEN E AND F TERMINATING AT COLD JOINT OF SLAB.
09/17/2010 BUILDING PRE-SLAB Partial Approval LEVEL B2 AREA 3-11/E-J CABLES AND MILD STEEL OK. SEVERAL PROBLEMS WITH THE ELECTRICAL CONDUITS IN THIS AREA. MET WITH E.O.R. TO DISCUSS NECESSARY REPAIRS. OK TO PLACE CONCRETE WHEN SPECIAL INSPECTOR CONFIRMS CORRECTIONS TO ELECTRICAL.
09/16/2010 BUILDING PRE-SLAB Partial Approval PROGRESS LEVEL B-2 AREA E-J / 3-11
09/15/2010 BUILDING PRE-SLAB Partial Approval NEED TO ADDRESS GSN'S FOR C.I.P. CONCRETE KEYNOTE #11, LINE I LEVEL B2 MISSING CHAMFER.

BANDED CABLES LINE I TOO CLOSE TO DECK AT MIDSPAN. SHOULD BE 1.25" TO CENTER OF CABLE.
09/08/2010 BUILDING PRE-SLAB Partial Approval LEVEL B3 COMPLETE