Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T10CM01509

Parcel: 11717023D


Addresses:

88 E BROADWAY BL


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T10CM01509

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
01/05/2011 EXCAVATION/LAYOUT REBAR & ZON Approved
10/26/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COMPLETION OF CAISSONS LEVEL 1 GRIDLINE 1-3 OK
10/14/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 3 each caissons ok to place on line 1
09/08/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 1) A-E/11-16 LEVEL B-3 PLACED OK
09/07/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PLACEMENT OF LEVEL B-3 AREA 11.5-16 / E-J OK.

OK TO PLACE AREA A-E/11.5-16
09/02/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) LEVEL B3 AREA 11.5-16/E-J STILL NEED VERTICALS FOR MASONRY WALL LINE H/13-14
08/31/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 1) AREA E-J/11.5-16 FINISH CORRECTIONS NOTED BY ?
2) FINISH ALL VERTICAL STEEL INSTALLATIONS FOR SW AND MASONRY WALLS
08/30/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BOTTOM MAT FOR LEVEL B3 AREA 11.5 - 16 / E-J OK. TOP MAT NOT DONE, COLS NOT IN.
08/24/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2ND MAT POUR PLACED OK (A-E/3-11.5).
08/24/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval AREA A-E / 3-11.5 OK TO PLACE WHEN SPECIAL INSPECTOR CONFIRMS FINAL SUMP BOX PLACEMENT, AND CORRECTION OF REMAINING NON-COMPLIANT WORK AS NOTED FROM 8-20.
08/20/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PROGRESS OK ON FOUNDATION MAT BUT STILL NEED VERITCALS FOR COLUMNS, SHEAR WALLS AND PERIMETER. SOME ADJUSTMENTS STILL REQUIRED FOR MAT AS NOTED IN SPECIAL INSP REPORT.
08/19/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PLANS AND SHOP DRAWING DISCREPANCIES WORKED OUT WITH JOHN GRENIER P.E. BOTTOM OF ELEVATOR PITS (TO TOP OF SUMPS0 OK TO PLACE WHEN SPECIAL INSPECTOR CONFIRMS FINAL PLACEMENT OF VERTICAL STEEL FOR SHAFT AND MISSING HORIZONTAL STEEL TIED TO VERTS WITHIN BOTTOM MAT.
08/18/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval INSPECTION OF BOTTOM MATT AT ELEVATOR PITS. NEED CLARIFICATION OF SOME PLAN NOTES AS THEY DON'T MATCH THE SHOP DRAWINGS AND THERE IS MUCH MORE STEEL INSTALLED IN WEST PIT THAN IS SHOWN ON PLAN.
08/17/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PLACEMENT OF CONCRETE OK. NEXT POUR SCHEDULED FOR 8/23. PLACEMENT OF STEEL INCOMPLETE FOR AREA A-E / 3-11.7. WILL RECALL FOR 8-18
08/16/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval REINFORCING STEEL FOR MATT FOUNDATION E-J / 3-11.7 OK PENDING FINAL ADJUSTMENTS PER SPECIAL INSPECTION REPORT (SHEARWALL LAP SPLICE LENGTH).

OK TO PLACE CONCRETE
08/13/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BOTTOM MATT E-J / 3-11.7 OK PENDING VERIFICATON OF STEEL STRENGTH. TOP MAT SUBSTANTIALLY COMPLETE BUT REQUIRES RE-INSPECTION. VERTICAL STEEL STILL BEING PLACED.
08/11/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval MILL CERTS FROM CMC (REBAR MANUFACTURER) SHOWING THAT SEVERAL HEATS OF STEEL MEET 75 KSI TENSILE STRENGTH REQUIREMENT BUT INDICATE STEEL WAS MIS-LABELED. FURTHER DOCUMENTATION IS NECESSARY FROM CMC TO PROVE THAT EACH SHIPMENT OF REBAR DID IN FACT COME FROM SPECIFIED HEATS.

BOTTOM PLACEMENT FROM 3 - 11.7 / E - J SUBSTANTIALLY COMPLETE PENDING VERIFICATION OF TENSILE STRENGTH.
08/10/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval REBAR PLACEMENT BEGUN AT LEVEL BE FOR MAT FOUNDATION. SHIPPING LABELS MARKED SHOWING STEEL IS 75 KSI BUT STAMP ON REBAR SHOWS IT AS 60 KSI. PLANS REQUIRE 75 KSI IN MAT. DISCREPANCY BROUGHT TO ATTENTION OF NICK CAP ON SITE.