Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T10CM01509
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/05/2011 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
10/26/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COMPLETION OF CAISSONS LEVEL 1 GRIDLINE 1-3 OK | |
10/14/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 3 each caissons ok to place on line 1 | |
09/08/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1) A-E/11-16 LEVEL B-3 PLACED OK | |
09/07/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PLACEMENT OF LEVEL B-3 AREA 11.5-16 / E-J OK. OK TO PLACE AREA A-E/11.5-16 |
|
09/02/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) LEVEL B3 AREA 11.5-16/E-J STILL NEED VERTICALS FOR MASONRY WALL LINE H/13-14 |
|
08/31/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1) AREA E-J/11.5-16 FINISH CORRECTIONS NOTED BY ? 2) FINISH ALL VERTICAL STEEL INSTALLATIONS FOR SW AND MASONRY WALLS |
|
08/30/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BOTTOM MAT FOR LEVEL B3 AREA 11.5 - 16 / E-J OK. TOP MAT NOT DONE, COLS NOT IN. | |
08/24/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 2ND MAT POUR PLACED OK (A-E/3-11.5). | |
08/24/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | AREA A-E / 3-11.5 OK TO PLACE WHEN SPECIAL INSPECTOR CONFIRMS FINAL SUMP BOX PLACEMENT, AND CORRECTION OF REMAINING NON-COMPLIANT WORK AS NOTED FROM 8-20. | |
08/20/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PROGRESS OK ON FOUNDATION MAT BUT STILL NEED VERITCALS FOR COLUMNS, SHEAR WALLS AND PERIMETER. SOME ADJUSTMENTS STILL REQUIRED FOR MAT AS NOTED IN SPECIAL INSP REPORT. | |
08/19/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PLANS AND SHOP DRAWING DISCREPANCIES WORKED OUT WITH JOHN GRENIER P.E. BOTTOM OF ELEVATOR PITS (TO TOP OF SUMPS0 OK TO PLACE WHEN SPECIAL INSPECTOR CONFIRMS FINAL PLACEMENT OF VERTICAL STEEL FOR SHAFT AND MISSING HORIZONTAL STEEL TIED TO VERTS WITHIN BOTTOM MAT. | |
08/18/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | INSPECTION OF BOTTOM MATT AT ELEVATOR PITS. NEED CLARIFICATION OF SOME PLAN NOTES AS THEY DON'T MATCH THE SHOP DRAWINGS AND THERE IS MUCH MORE STEEL INSTALLED IN WEST PIT THAN IS SHOWN ON PLAN. | |
08/17/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PLACEMENT OF CONCRETE OK. NEXT POUR SCHEDULED FOR 8/23. PLACEMENT OF STEEL INCOMPLETE FOR AREA A-E / 3-11.7. WILL RECALL FOR 8-18 | |
08/16/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | REINFORCING STEEL FOR MATT FOUNDATION E-J / 3-11.7 OK PENDING FINAL ADJUSTMENTS PER SPECIAL INSPECTION REPORT (SHEARWALL LAP SPLICE LENGTH). OK TO PLACE CONCRETE |
|
08/13/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BOTTOM MATT E-J / 3-11.7 OK PENDING VERIFICATON OF STEEL STRENGTH. TOP MAT SUBSTANTIALLY COMPLETE BUT REQUIRES RE-INSPECTION. VERTICAL STEEL STILL BEING PLACED. | |
08/11/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | MILL CERTS FROM CMC (REBAR MANUFACTURER) SHOWING THAT SEVERAL HEATS OF STEEL MEET 75 KSI TENSILE STRENGTH REQUIREMENT BUT INDICATE STEEL WAS MIS-LABELED. FURTHER DOCUMENTATION IS NECESSARY FROM CMC TO PROVE THAT EACH SHIPMENT OF REBAR DID IN FACT COME FROM SPECIFIED HEATS. BOTTOM PLACEMENT FROM 3 - 11.7 / E - J SUBSTANTIALLY COMPLETE PENDING VERIFICATION OF TENSILE STRENGTH. |
|
08/10/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | REBAR PLACEMENT BEGUN AT LEVEL BE FOR MAT FOUNDATION. SHIPPING LABELS MARKED SHOWING STEEL IS 75 KSI BUT STAMP ON REBAR SHOWS IT AS 60 KSI. PLANS REQUIRE 75 KSI IN MAT. DISCREPANCY BROUGHT TO ATTENTION OF NICK CAP ON SITE. |