| 08/02/2010 | ELECTRIC - FINAL | Approved | IVRS - Inspection :* | |
| 07/23/2010 | ELECTRIC - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) ROOF DISCONNECT PUT BOND BUSHINGS 2) PV INTERVERTER DISCONNECT EMT PIPE NOT IN CONNECTOR ALL THE WAY 3) PV METER BASE LUG, SCRAPE OFF PAINT |
|