Permit: T10CM00578

Parcel: 10511043B

Inspection Status: Approved

Inspection History: PLUMBING - ROUGH, SOIL

Date Description Inspector Results Comments
08/19/2010 PLUMBING - ROUGH, SOIL Approved IVRS - Inspection :*
08/17/2010 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
1) INSULATION TO BE INSTALLED IN A WORKMANSHIP LIKE MANNER CONFORMING TO THE INSTALLATION STANDARD ESTABLISHED BY THE MANUFACTURER
2) AT P.O.C. TO DWV. PIPING TO BE INSTALLED IN PRACTICAL ALIGNMENT WITH NO BACK PITCHED SECTIONS
08/12/2010 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
THE PLUMBER HAS NOT FOLLOWED THE PLAN INTO EITHER THE DWV OR THE WATER PIPING. NO REDLINES ON SITE.
NO PROVISION MADE FOR INSULATION
A BLAKE TEE IS NOT LISTED TO BE INSTALLED IN A HORIZONTAL POSITION ON ITS SIDE
N/H TO BE SUPPORTED WITHIN 18" OF EACH COUPLING