Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/10/2010 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* 1) SPOKE WITH RAOY FOOTING COMPLETE NORTH AND WEST SIDES |
|
| 06/02/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) OK TO PROCEED |
|
| 05/25/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) RECALL TO VERIFY 20" LAPS, WILL BE POURED IN SECTIONS |
|
| 05/14/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* REFALL 2/3 OK FRONT PORCH FOOTERS REFALL 1/3 NOT PER PLAN UNDERPIN AND RECALL PRIOR TO POUR. |
|
| 05/11/2010 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* STRUCTUAL: 1) PORCH 4 X 8 BEAM ON PLAN NOT WHATS INSTALLED 2) REAR ENCLOSED ROOF, WHAT ARE RAFTERS SIZE DON'T HAVE MINIMUM ROOF PITCH 3) FTGS FOR PORCH AND REAR ROOM BEARING TO BE VERIFIED. SLOPE ON PLAN IS TO THE NORTH ELECTRICAL: 1) ALL WIRING IS COVERED 2) CIRCUITS NOT LABELED IN SERVICE PANEL 3) AS LIVING SPACE WALL RECEPTS TO FOLLOW SPACING REQUIREMENTS, 6'-0" FROM AN OPENING 12'-0" ON CENTER AFTER THAT 4) CAN'T USE A/C ROOF DISCONNECT AS A JUNCTION BOX FOR BATHROOM CIRCUIT (GFCI AND LIGHTING) PLUMBING: 1) UNCOVER SEWER LINE AT NEW BATHROOM 2) WHERE IS CLEANOUT FOR THAT BRANCH. HOW WAS BATHROOM PLUMBED (UNDERGROUND) ?, VENTING 3) LOCATE MAIN HOUSE CLEANOUT 4) T & P LINE FOR H20 HTR TERMINATION |