Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
Permit Number - T10BU01891
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/31/2011 | GRADING - INTERMEDIATE | Approved | Approved | |
08/10/2011 | GRADING - INTERMEDIATE | Partial Approval | Swale for WH area in front of building OK to plant. | |
08/02/2011 | GRADING - INTERMEDIATE | Continued | Parking lot ready fro paving. | |
07/29/2011 | GRADING - INTERMEDIATE | Continued | Subgrade base in place, ready to pave. | |
07/29/2011 | GRADING - INTERMEDIATE | Partial Approval | OK to pur conc. sidewalk from ROW to parking lot. | |
07/27/2011 | GRADING - INTERMEDIATE | Continued | COntractor began placeing subbase today, I reminded them of the water harvest requirements, he is awhare of them. | |
07/21/2011 | GRADING - INTERMEDIATE | Continued | Contractor forming sidewalk in front and on side of building, OK to pour, also grading for parking lot, rminded contractor about waterharves areas and grades associated with them. | |
07/18/2011 | GRADING - INTERMEDIATE | Partial Approval | OK to backfill 12" HDPE pipe for storm. | |
07/06/2011 | GRADING - INTERMEDIATE | Continued | Site grading will begin this week for the parking lot. Reminded contractor of the water harvest requirements. | |
06/22/2011 | GRADING - INTERMEDIATE | Continued | All the curb work is complete, work continues on building. | |
06/14/2011 | GRADING - INTERMEDIATE | Continued | Steel being erected for building, curbing in parking lot under construction. | |
06/08/2011 | GRADING - INTERMEDIATE | Continued | Curbing for parking lot and water harvest being installed. | |
05/26/2011 | GRADING - INTERMEDIATE | Continued | Contractor working on building foundation, no site work at this time. | |
05/19/2011 | GRADING - INTERMEDIATE | Continued | Lot and basin is rough graded, contractor working on foundation and utilities to new building. | |
05/17/2011 | GRADING - INTERMEDIATE | Continued | Contractor working on building pad, has basin roughed in. | |
05/12/2011 | GRADING - INTERMEDIATE | Continued | Controls stakes are in contractor cutting for building pad. | |
05/03/2011 | GRADING - INTERMEDIATE | Continued | No grading activity at this time. |