Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
| Date |
Description |
Inspector |
Results |
Comments |
| 08/31/2011 |
STORMWATER FOLLOW-UP INSP |
|
Approved |
Approved |
| 08/02/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Silt fence still down needs immediate attention |
| 07/29/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Ask contractor to repair silt fence at ROW. |
| 07/21/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Silt fence needs to be repaired. |
| 07/06/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Storms over the weekend damaged some of the sitl fence onsite, contractor will replace and repair as needed. |
| 06/30/2011 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
General contractor not onsite still needs to repair silt fence and clean up site from trash. |
| 06/22/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Silt fence needs maintenance. |
| 06/14/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Repair sitl fence as needed, install conc washout area, need a dumpster for trash/waste on project. |
| 06/08/2011 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
Told contractor to provide and washout area for concrete trucks, and maintain silt fence that has fallen down. |
| 05/26/2011 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
Controls in place and in good cond. |
| 05/19/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Silt fence needs to be maintained along west edge of project. |
| 05/17/2011 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
Controls in place and in good cond., will need to add a conc. washout area when building const. begins. |