Permit: T10BU01806

Parcel: 11308208F


Addresses:

2802 N 1ST AV


Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Permit Number - T10BU01806

Inspection Description - GRADING - INTERMEDIATE

Inspection Status - Approved

Date Description Inspector Results Comments
04/18/2012 GRADING - INTERMEDIATE Approved
04/13/2012 GRADING - INTERMEDIATE Continued FOLLOW UP ON INSPECTION FOR FINAL APPROVAL. COMPLETE ALL SITE WORK PER YOUR APPROVED GRADING PLAN.
03/05/2012 GRADING - INTERMEDIATE Continued 1) VERIFIED THE APPROVED REVISION WAS CONSTRUCTED IN THE FIELD. ALL CHANGES MADE WERE APPROVED BY THE CITY OF TUCSON.
2) STOCKPILE ON SITE, NEED SEDIMENT CONTROLS TO ENSURE SOIL STAYS ON SITE.
3) NEED TO RE-ESTABLISH THE STABILIZED CONSTRUCTION ENTRANCE/EXIT
4) NEED TO SWEEP TRACKING OFF GLENN MORE OFTEN.
03/02/2012 GRADING - INTERMEDIATE Continued 1) REMOVE STOCKPILE ALONG EAST SIDE OF SITE AND/OR PLACE SEDIMENT CONTROLS AROUND IT.
2) RE-ESTABLISH SEDIMENT CONTROLS (SILT FENCE) ALONG WESTERN EDGE OF PROPERTY
3) SWEEP UP TRACKING OFF GLENN - ADD A STABILIZED ENTRANC/EXIT AT GLENN
4) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED
5) NEED TO VERIFY AND APPROVE THE CHANGE TO THE GAS CANOPY ROOF DRAIN TIE-IN/BUBBLER BOX . ENSURE COT APPROVED REVISION.
02/08/2012 GRADING - INTERMEDIATE Continued CONTRACTOR COMPLETED STORM PIPE ALONG NORTH SIDE.
GAS CANOPY ROOF DRAIN CONNECTION WILL CHANGE PER THE ENGINEER OF RECORD.

NO SIGNIFICANT STORM WATER COCNERNS AT THIS TIME
02/07/2012 GRADING - INTERMEDIATE Continued 1) CONTRACTOR FORMING TRANSITION DRAINAGE STRUCTURE AT SE CORNER OF SITE/INSPECTION AND COMPACTION TESTING DONE BY COT PIA INSPECTOR MARTIN HERNANDEZ.
2) STORM DRAIN PIPING AND CANOPY ROOF DRAIN TIE-IN BEING INSTALLED ALONG THE NORTH SIDE OF SITE.
3) CHANGE TO ROOF DRAIN TIE (INVERT 15" TOO LOW) NEED A REVISED/APPROVED PLANS.
4) RE-ESTABLISH SILT FENCE ALONG WEST PERIMETER . REMOVE CONSTRUCTION DEBRIS FROM FENCE.
01/09/2012 GRADING - INTERMEDIATE Continued 1) WALKED THE SITE, GROUND PREPED FOR STORM DRAIN TRANSITION WEIR WALL - NEED TO SEE INSTALL PRIOR TO COVER.
2) SOME SITE WORK DONE ALONG WEST RET'DET BASIN.
3) STORM PIPE WORK NEXT WEEK, NEED TO SEE INSTALL.
4) SITE WORK BEING DONE ON DRAINAGE BEHIND THE BLDG.
5) ENSURE STORM WATER REQUIREMENTS ARE TAKEN CARE OF; SWEEP STREETS OFTEN AND DOCUMENT SELF INSPECTIONS.
6) CALL FOR INSPECTION FOR CANOPY ROOF DRAIN TO STORM DRAIN TRANSITION.
12/06/2011 GRADING - INTERMEDIATE Continued 1) VERIFY INSTALL OF 150 LF OF 36"X3 SRP ALONG SOUTH SIDE OF SITE.
TRENCH WAS COMPACTED, PIPE WAS BEDDED AND GRADED.
NEOPRENE GASKET USED W/BOLTED COLLAR FOR CONNECTED PIPE.
2) INSTALL SEDIMENT CONTROLS ON S. SIDE OF EAST LOT.
3) INSTALL CONSTRUCTION ENTRANCE AT EACH ENTRANCE/EXIT IN ORDER TO REDUCE TRACKING.
5) REMOVE SOIL FROM CURB LINE
12/01/2011 GRADING - INTERMEDIATE Continued 1) CONTRACTOR EXCAVATING TRENCH FOR 3-36" SRP PIPES THAT WILL TIE0IN TO AN EXISTING CULVERT (APPROX 145CFS) PICTURES TAKEN.
2) PROVIDE A COPY OF THE PIPE MANUFACTURER'S INSTALLATION INSTRUCTIONS FOR RECORDS.
3) RET/DET BASIN ALONG 1ST AVE BEING ROUGHED IN.
4) ENSURE GLENN ST IS SWEPT ON A ROUTINE BASIS. SWEEP UP TRACKING AS NECESSARY.
11/17/2011 GRADING - INTERMEDIATE Continued 1) CONTRACTOR INSTALLING SEWER LINE CONNECTION.
2) CONTRCTOR FORMING RETAINING WALL/BLDG BACK WALL ON EAST SIDE.
3) CONTRACTOR ERECTING GAS CANOPY, STEEL WORK FOR CANOPY.
4) TRENCH HAS BEEN ROUGHED IN FOR STORM DRAIN PIPING.
5) CONTINUE TO SWEEP TRACKING OF SOIL OFF PUBLIC ROADWAYS AS APPLICABLE.
6) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME