Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 07/15/2011 |
GRADING - INTERMEDIATE |
|
Approved |
|
| 06/20/2011 |
GRADING - INTERMEDIATE |
|
Partial Approval |
THE PAVING OPERATION FOR THIS SITE WAS COMPLETED TODAY, THE MINOR REMAINING ITEMS WILL BE ADDRESSED DURING THE REMAINDER OF THIS WEEK. I LOOKED AROUND THE SITE TO SEE IF THERE WERE ANY ADDITIONAL ITEMS THAT NEEDED TO BE ADDRESSED AT THIS TIME, THERE WAS NOTHING. THE CONTRACTOR HAS ADVISED THAT THIS SITE WILL BE OPENNED IN THE NEXT TWO WEEKS IF ALL GOES WELL, MAYBE BY THE FIRST WEEK OF JULY. THERE ARE NO CONCERNS AT THIS TIME FOR ANYTHING ON THE SITE. DID ASK THAT THE CONTRACTOR GET APPROVAL FOR THE FORMS THAT HAVE BEEN PLACED FOR THE VERTICAL CURB TRANSITION THAT IS TO BE POURED ON THE SOUTHSIDE OF THE NEW DRIVEWAY OPENNING LOCATED AT THE SOUTHWEST CORNER OF THE SITE. THEY HAVE IT LAID OUT TO TIE INTO THE LOWER AREA OF THE EXISTING TRANSITION WHICH MAY CREATE SOME ISSUES ONCE THE FORMS HAVE BEEN REMOVED. |
| 06/13/2011 |
GRADING - INTERMEDIATE |
|
Continued |
MET ONSITE WITH THE CONTRACTOR AND DISCUSSED WHAT HE HAS SCHEDULED FOR THE NEXT 2 WEEKS. THEY WILL BEGIN TO POUR THE CONCRETE PAVEMENT SECTIONS AND SHOULD BE COMPLETE BY MID WEEK NEXT WEEK. THEY HAVE ALSO REMOVED THE SECTION OF WALL AT THE NORTHWEST SIDE WHERE THE SIDEWALK IS TOO EXTEND OUT TOO HARRISON RD. THIS WAS MISSED DURING THE CONSTRUCTION PHASE OF THIS SITE, I REMINDED THEM THAT IS REQUIRED BY ZONING AND NEEDED TO BE INSTALLED. |
| 06/09/2011 |
GRADING - INTERMEDIATE |
|
Continued |
MET ONSITE WITH THE CONTRACTOR, THEY HAVE CUT MOST OF THE GRADE FOR THE FINISH PARKING LOT AND WILL BE WORKING ON POURING THE CONCRETE PARKING LOT STARTING NEXT WEEK. |
| 06/03/2011 |
GRADING - INTERMEDIATE |
|
Continued |
MET ONSITE WITH THE CONTRACTOR TO DISCUSS WHAT HE WILL BE DOING OVER THE NEXT TWO WEEKS. HE WILL HAVE THE GRADING CONTRACTOR COME IN AND COMPLETE THE GRADING OF THE SITE, ENSURING THAT WE MEET THE WATER HARVESTING ASPECTS. THIS WORK SHOULD BE COMPLETED BY THE END OF THIS NEXT WEEK AND THE CONCRETE PAVING OPERATION TO FOLLOW ON THE FOLLOWING WEEK. |
| 05/04/2011 |
GRADING - INTERMEDIATE |
|
Continued |
LOOKED OVER THE SIGT AND DISCUSSED WITH THE DEVELOPER WHAT INSPECTION WOULD NEED TO BE SCHEDULE BY THEM IN THE FUTURE. THIS SITE WILL BE MONITORED, THE NEXT SCHEDULED INSPECTION WILL BE FOR THE RAINWATER INTERMEDIATE. |