Permit: T10BU01609

Parcel: 21114007C

Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Date Description Inspector Results Comments
02/25/2011 GRADING - INTERMEDIATE Approved
01/11/2011 GRADING - INTERMEDIATE Partial Approval Premeter fence under construction, Pad will be ready to pour later in week.
12/15/2010 GRADING - INTERMEDIATE Partial Approval Received EL cert for subgarde on PAD, contractor will install elec. and pour conc on pad next.
12/06/2010 GRADING - INTERMEDIATE Partial Approval Rip rap placed for pad is approved, I let John know today that they will need to stabilize the entire site at the end of the project to satisfy SWPPP requirements.
John said he will get me El certs for the pad next week.
12/03/2010 GRADING - INTERMEDIATE Partial Approval OK to place rip rap at pad, fill slopes Ok for slope at 4:1
12/02/2010 GRADING - INTERMEDIATE Continued Sunpower preparing pad fopr El Cert, compaction and rip rap toe down, should be ready by tomorrow.
12/01/2010 GRADING - INTERMEDIATE Continued Met with contractor on site today, working on pad, and drilling holes for solar panels, special inspector on site to verify depth of holes and compaction for pad.