Inspection Status: Approved

Inspection History: ENGINEERING PRE-CONSTRUCTION

Date Description Inspector Results Comments
12/06/2010 ENGINEERING PRE-CONSTRUCTION Approved Met with LJ McCreary at the site today to discuss NPPO, storm controls and grading activity. I told him we will need a report from the LS Arch regarding the NPPO. We discussed the vertical rock walls, he needs his geo-tech engineer to address wheather treatment is needed and if the swale along the top is necessary.
12/02/2010 ENGINEERING PRE-CONSTRUCTION Continued no pre-con conducted on this site, contractor has been working for about 3 weeks